INSP-Final Inspection | 9/2/2016 | 9/2/2016 | 9/2/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 8/24/2016 | 8/25/2016 | 8/26/2016 | A | FAIL |
Troy Cobbley
|
|
|
Need NFPA 72 record of completion, need map at the FACP and need as-builts resubmitted since the provided as-builts do not match existing conditions.
|
Issue and Print Permit | | | 8/5/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/5/2016 | | 8/5/2016 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (Lee) | 8/4/2016 | | 8/4/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 8/4/2016 | | PASS |
|
|
|
|
Alarm Plan Check | 8/4/2016 | | 8/4/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/4/2016 | | DONE |
|
|
|
Plans approved with review comments.
|
Application received | | | 8/3/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2016 2:51PM
|
Telephone call | | | 8/3/2016 | | DONE |
|
|
|
Prior to submittal, Dante called to indicate Simplex will be modifying the system at DArigold. At this time, they are unaware of the details of the existing system and are not able to test the system to determine current loads but intend to meet the requirements of current code. He wanted to know if they can submit now with what they do know but provide documentation in the form of as builts. I informed them that this would be allowed. If a considerable amount of changes are required, a plan modification will be needed prior to completion.
|