INSP-Final Inspection | 12/1/2016 | 12/2/2016 | 12/2/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 11/28/2016 | 11/30/2016 | 11/30/2016 | P | NR |
Katie Marron
|
|
|
Fire alarm portion not ready. Not prepared for forward flow test.
Tested inspectors test/flow switch and bell function. Checked escutcheons
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2016 | 11/30/2016 | 11/30/2016 | P | PASS |
Katie Marron
|
|
|
Hydrostatic test completed saitsfactory.
|
INSP-Sprinkler Rough-in | 11/9/2016 | 11/9/2016 | 11/9/2016 | P | PASS |
Katie Marron
|
|
|
Completed rough-in of grid ceiling. Ok to cover.
|
INSP-Sprinkler Rough-in | 10/24/2016 | 10/24/2016 | 10/24/2016 | A | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping complete, another rough to cover inspection will need to be performed for cover after ceiling grid and finish pendant heads are installed.
|
Sprinkler Plan Check | 8/25/2016 | | 8/25/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/25/2016 | | DONE |
Tim Frost
|
|
|
|
Issue and Print Permit | | | 8/25/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/25/2016 | | 8/25/2016 | | DONE |
Brittany Hill
|
|
|
|
1st review completed | | | 8/25/2016 | | PASS |
|
|
|
|
Intake Approval | | | 8/16/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/16/2016 | | 8/16/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 15 2016 4:43PM
|