INSP-Final Inspection | 1/4/2017 | 1/5/2017 | 1/5/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 1/3/2017 | 1/4/2017 | 1/4/2017 | P | CANC |
Jim Page
|
|
|
Inspection request rescheduled due to scheduling conflict.
|
INSP-Sprinkler Rough-in/Hydro | 12/27/2016 | 12/28/2016 | 12/28/2016 | A | PASS |
Jim Page
|
|
|
Hydrostatic test complete for overhead fire sprinkler piping.
|
INSP-Sprinkler Rough-in/Hydro | 12/14/2016 | 12/14/2016 | 12/14/2016 | P | PASS |
Jim Page
|
|
|
Underground supply hydro test complete
|
INSP-Supply line flush | 12/14/2016 | 12/14/2016 | 12/14/2016 | P | CANC |
Jim Page
|
|
|
Inspection request is for underground hydro, this inspection request cancelled the proper inspection request will be generated.
|
INSP-Supply line flush | 12/7/2016 | 12/9/2016 | 12/9/2016 | A | DONE |
Jim Page
|
|
|
Supply line flush complete
|
INSP-Supply line flush | 12/6/2016 | 12/7/2016 | 12/7/2016 | A | CANC |
Jim Page
|
|
|
Supply line flush was suppose to be scheduled for 09DEC2016, this request cancelled
|
INSP-Supply line flush | 11/21/2016 | 11/22/2016 | 11/22/2016 | P | PASS |
Jim Page
|
|
|
Inspection request was for a rough to cover inspection for the underground supply, not a supply line flush, underground supply approved for cover.
|
Permit Ready to Issue | | | 10/24/2016 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 10/24/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/24/2016 | | 10/24/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Sprinkler Plan Check | 10/20/2016 | | 10/20/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2016 | | DONE |
Tim Frost
|
|
|
|
Early Start | | | 10/18/2016 | | PASS |
|
|
|
*** FIELD INSPECTOR *** Just for the underground only
|
Miscellaneous action | | | 10/17/2016 | | PEND |
|
|
|
Project on hold waiting for Jim to return my call. I need a better pump curve then what Pentair provided. In addition, I need to go over the annotations with Jim and tell him as built drawings are required.
|
Intake Approval | | | 10/3/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/3/2016 | | 10/3/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/3/2016 | | 10/3/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 10/3/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/3/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Sprinkler Plan Check | 8/29/2016 | | 8/29/2016 | | FAIL |
Tim Frost
|
|
|
Failed on prescreen. High piled storage forms are required. Sent email to Ken.
|
Intake Approval | | | 8/25/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/25/2016 | | 8/25/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 15 2016 6:58PM
|