INSP-Final Inspection | 10/14/2016 | 10/17/2016 | 10/17/2016 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Sprinkler Rough-in/Hydro | 9/30/2016 | 9/30/2016 | 9/30/2016 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 9/30/2016 | 9/30/2016 | 9/30/2016 | P | CANC |
Jim Page
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
Intake Approval | | | 8/18/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 8/18/2016 | | 8/18/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/18/2016 | | 8/18/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/18/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/18/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 8/18/2016 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 8/18/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/18/2016 | | 8/18/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 8/17/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 17 2016 1:18PM
|