Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberFIR16-00563
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 505 W IDAHO ST
Project Name5th & Idaho Apartments
Customer Number 
ePlanReviewYes
Description
[5th & Idaho Apartments]
The fire sprinkler scope of work consists of protecting a six level building per NFPA 13. There is parking garage in the basement. The basement part of the first floor are protected with a dry system. The first floor also has a retail space. The remainder of the first floor is residential and incidental use areas. The residential areas of the first floor have mezzanine. Floors two – five are residential and utilize CPVC piping and residential sprinklers. There are two manual wet standpipes. Standpipe one has floor level control valves for the sprinklers. All floors are designed as tree type systems.

• This building is NOT considered a high rise. The top floor is 61’-9 3/8” above grade.
• This building is over 30’ and therefore, requires standpipes in all required stairwells.
• NFPA 13R is limited to 60’ (Ref: NFPA 13R: 1.1). The building is 72’4” ± which, does NOT qualify to be protected under NFPA 13R and therefore is protected per NFPA 13.
• This building does NOT use the special City of Boise ordinance.
• Exposed piping is steel. Concealed piping on floors 2-5 is CPVC.


Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.


[BLD16-00563] – Bldg #1: Construct a five story plus 1 story basement building consisting of approximately 101,000 GSF with a residential area of approximately 70,500 GSF including ancillary space. The structure will be a concrete parking garage, plaza and street grade concrete lid with wood framing systems for floors one through five along with the roof deck. The exterior envelope will be brick, EIFS, aluminum storefront, vinyl windows and a membrane roof system.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/4/20192/4/20192/4/2019APASS
DetailsJim Page
Final fire sprinkler inspection complete.
INSP-Sprinkler Rough-in11/14/201811/14/201811/14/2018PPASS
DetailsTroy Cobbley
Forward Flow test passed. TVFP is providing a more permanent solution for yearly testing.


coordinate forward flow of the back flow with Troy Nelson Phone #: ###-#### >> Inspection requested via web by Christophe Wilson
INSP-Final Inspection11/12/201811/13/201811/13/2018APASS
DetailsTim Frost
Performed tamper and flow tests. All ok
Looked at basement. ok
Walked around spot checking sprinklers. ok

*** They need to add signs to the risers which will need to be coordinated with fire alarm.

*** They need to perform a forward flow test.





This is inspection for TCO at Phase 1 as directed by General Contractor. Please call Lonnie with Time frame. Will include tampers flows and dry system trip test to put all fire sprinkler systems in service. Phone #: ###-#### >> Inspection requested via web by Jeff Packham
INSP-Sprinkler Rough-in/Hydro10/23/201810/24/201810/24/2018ADONE
DetailsJim Page
Hydrostatic test for levels 1, 2 and 3 are complete.

Coordinate Hydro with Lonnie Greenfield Phone #: ###-#### Inspection requested via web by Christophe Wilson
INSP-Sprinkler Rough-in10/22/201810/22/201810/22/2018PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above hardlids on level 1 complete, approved for cover.

Please coordinate inspection with Lonnie Greenfield Phone #: ###-#### Inspection requested via web by Christophe Wilson
INSP-Sprinkler Rough-in/Hydro10/8/201810/9/201810/9/2018APASS
DetailsTroy Cobbley
Overhead hydro for the 4th and 5th floors witnessed with no visible loss at the guages.


Please coordinate hydro with Lonnie Greenfield Phone #: ###-#### Inspection requested via web by Christophe Wilson
INSP-Sprinkler Rough-in/Hydro9/24/20189/25/20189/25/2018APART
DetailsJim Page
Hydrostatic test for standpipe 1 and 2, basement wet system and dry system witnessed, no pressure loss observed at riser provided gauges.

dry Coordinate inspection with Lonnie Greenfield Phone #: ###-#### Inspection requested via web by Christophe Wilson
INSP-Supply line flush9/17/20189/20/20189/20/2018APASS
DetailsTim Frost
Coordinate Fire Service flush with Lonnie Greenfield Phone #: ###-#### >> Inspection requested via web by Christophe Wilson

___________________
Flush was ok
INSP-Sprinkler Rough-in/Hydro9/10/20189/11/20189/11/2018APASS
DetailsJim Page
this is an underground hydro. Lonnie is our foreman Phone #: ###-#### >> Inspection requested via web by Brad Bettencourt

I also looked at the underground in the parking garage. All was ok. Hydro of underground OK.
INSP-Sprinkler Rough-in8/21/20188/22/20188/22/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located in level 1 condos complete, level 1 condos approved for cover. Fire sprinkler pipng for trash shutes approved for cover as well.

First Floor Rough in Phone #: ###-#### Inspection requested via web by Christophe Wilson
INSP-Sprinkler Rough-in7/24/20187/24/20187/24/2018PPART
DetailsJim Page
Rough to cover inspection for uderground supply complete, approved for cover.
INSP-Sprinkler Rough-in7/12/20187/13/20187/13/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above drop down ceilings in apartments complete, level 5 drop down ceiling in apartments approved for cover.

on level 5 completecover inspection Phone #: ###-#### Inspection requested via web by Christophe Wilson
INSP-Sprinkler Rough-in6/13/20186/14/20186/14/2018APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above hardids on levels 4 and 5 complete, approved for cover.



Cover inspection for 4th ; 5th Floor Phone #: ###-#### Inspection requested via web by Christophe Wilson
INSP-Sprinkler Rough-in5/3/20185/3/20185/3/2018PPART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping above hardlids on levels 2 and 3 complete, hardlids on levels 2 and 3 approved for cover, drop in ceilings will be inspected at a later date.

Coordinate Inspection With Lonnie Phone #: ###-#### Inspection requested via web by Christophe Wilson
Plan Modification Accepted  2/22/2018 DONE
Plan assigned to (Tim)2/22/2018 2/22/2018 DONE
DetailsTim Frost
Sprinkler Plan Check2/22/2018 2/22/2018 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  2/22/2018 DONE
Permit Ready to Issue  2/22/2018 DONE
DetailsChristina Prado
DO NOT RE-ISSUE - PLAN MOD APPROVED
(F) Reprint permit  2/22/2018 DONE
CHANGE STATUS TO (ISS)  2/22/2018 DONE
(F) Reprint permit  2/22/2018 DONE
INSP-Final Inspection7/25/20177/26/20177/26/2017ACANC
DetailsJim Page
Wrong FIR permit called in, verified with Mike Phone #: ###-####, this request is cancelled.
Miscellaneous action  5/12/2017 DONE
***IMPORTANT*** DO NOT FINAL THIS PERMIT
There is a AMMR #2 which has to be resolved prior to finalizing this permit. The FPC has been notified multiple times regarding this item including today.

Sprinkler Plan Check9/28/2016 9/28/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  9/28/2016 DONE
DetailsTim Frost
Permit Ready to Issue  9/28/2016 DONE
Issue and Print Permit  9/28/2016 DONE
Inspection Record Card- Fire9/28/2016 9/28/2016 DONE
DetailsCandy A. Nichols
Miscellaneous action  9/13/2016 DONE
as per Tim Frost-changed address from 503 W Idaho to 505 W Idaho
Sprinkler Plan Check9/7/2016 9/7/2016 FAIL
DetailsTim Frost
Failed on prescreen due to lack of occupancy descriptions.
Intake Approval  9/6/2016 PASS
Plan assigned to (Tim)9/6/2016 9/6/2016 DONE
DetailsTim Frost
Application received  8/31/2016 DONE
Application submitted via PDS Online on Aug 31 2016 9:49AM