Permit Information
Permit NumberFIR16-00569
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 500 S CAPITOL BLVD
Project NameRICHARD RESTAURANT T.I.
Customer Number 
ePlanReviewYes
Description
[Richard Restaurant TI]
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration.

[BLD16-01992] - A tenant improvement of a 3,322 sf restaurant on the first floor and 2 catering rooms one 76 sq ft the other 40 sq ft on the second floor permitted under the gray shell of an under construction hotel BLD16-00147. All new MEP, interior walls and interior finishes to create a dining space, bar and commercial kitchen. No structural members to be disturbed. Common bathrooms provided by hotel in lobby area. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **ajs**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/22/201612/22/201612/22/2016PPASS
DetailsJim Page
Final fire sprinkler inspection for area of work for this permit complete, notes for hotel have been added to this permit from past inspection requests due to permit number confusion.
INSP-Sprinkler Rough-in11/9/201611/9/201611/9/2016PCANC
DetailsKatie Marron
Will be rescheduled for tomorrow. Arrived on site but contractor had left already for the day. Adam Phone #: ###-####
INSP-Sprinkler Rough-in11/7/201611/7/201611/7/2016PCANC
DetailsKatie Marron
Contact number provided was a discontinued number. Reschedule and provide correct contact information.
INSP-Sprinkler Rough-in10/21/201610/21/201610/21/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler on level 6 complete, city approved plans are notated with yellow highlighter, overhead fire sprinkler piping on level 6 approved for cover.
INSP-Sprinkler Rough-in10/12/201610/12/201610/12/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located at 3rd level east hallway complete, overhead fire sprinkler located in noted area approved for cover.
INSP-Sprinkler Rough-in10/7/201610/7/201610/7/2016PPASS
DetailsTroy Cobbley
See the second floor plans where I have notated with todays day the corridor system where piping can be covered.
INSP-Sprinkler Rough-in10/6/201610/6/201610/6/2016PPASS
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping located in the level 2 northeast corridor complete, overhead fire sprinkler piping located in the level 2 northeast corridor approved for cover.
INSP-Sprinkler Rough-in9/28/20169/28/20169/28/2016PPASS
DetailsJim Page
Rough to cover inspection for fire sprinkler piping located above hardlids in restroom and soffits in dining area complete, overhead fire sprinkler piping in noted area's approved for cover.
Permit Ready to Issue  9/12/2016 DONE
Issue and Print Permit  9/12/2016 DONE
Inspection Record Card- Fire9/12/2016 9/12/2016 DONE
DetailsChristina Prado
Intake Approval  9/9/2016 PASS
Plan assigned to (Tim)9/9/2016 9/9/2016 DONE
DetailsTim Frost
Sprinkler Plan Check9/9/2016 9/9/2016 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  9/9/2016 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  9/9/2016 DONE
DetailsTim Frost
Application received  9/8/2016 DONE
Application submitted via PDS Online on Sep 8 2016 8:56AM