INSP-Final Inspection | 2/28/2017 | 3/1/2017 | 3/1/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 2/28/2017 | 2/28/2017 | 2/28/2017 | P | CANC |
Jim Page
|
|
|
|
INSP-Final Inspection | 2/27/2017 | 2/27/2017 | 2/27/2017 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with Jeremy Phone #: ###-####, inspection request will be rescheduled after fire bell is installed.
|
INSP-Sprinkler Rough-in | 12/20/2016 | 12/21/2016 | 12/21/2016 | A | PASS |
Jim Page
|
|
|
Overhead fire sprinkler pipe tenting complete for piping located in attic spaces, piping in attic spaces approved for cover. Material used for tenting is clear plastic sheeting to cover pipe, blow in insulation will be applied at a later date after sheetrock is installed, prefered method for tenting is batting type insulation to help insure R38 stays over the top of fire sprinkler piping and to maintain the clear pocket between the piping and the sheetrock for radiant heat.
|
INSP-Sprinkler Rough-in | 12/6/2016 | 12/7/2016 | 12/7/2016 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping complete, overhead fire sprinkler located between floors is approved for cover, fire sprinkler piping located in attic spaces cannot be covered until tenting insulation/tenting inspection is complete and passed.
|
Sprinkler Plan Check | 11/23/2016 | | 11/23/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/23/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/23/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/23/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/23/2016 | | 11/23/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 11/22/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/22/2016 | | 11/22/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/22/2016 | | 11/22/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 11/22/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/22/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Miscellaneous action | | | 10/13/2016 | | DONE |
|
|
|
Asked the FPC the status of this project.
|
Miscellaneous action | | | 10/13/2016 | | DONE |
|
|
|
FPC said the project will be designed soon.
|
Application received | | | 9/12/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 12 2016 9:23AM
|