INSP-Final Inspection | 4/24/2018 | 4/26/2018 | 4/26/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
|
INSP-Sprinkler Rough-in/Hydro | 4/24/2018 | 4/26/2018 | 4/26/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for levl 4 wet system witnessed, no pressure loss observed at rised provided gauge.
|
INSP-Final Inspection | 4/18/2018 | 4/23/2018 | 4/23/2018 | A | PART |
Jim Page
|
|
|
Fire sprinkler heads/escutcheons on levels 5, 3, and 2 are complete, still need to test flow switches/tampers on all floors.
|
INSP-Sprinkler Rough-in/Hydro | 4/23/2018 | 4/23/2018 | 4/23/2018 | A | FAIL |
Jim Page
|
|
|
Hydrostatic test for level 4 will need to be completed after repairs are made. Relocate heads that are blocked by drain piping on level 1 dry system.
|
INSP-Sprinkler Rough-in/Hydro | 4/18/2018 | 4/20/2018 | 4/20/2018 | P | PART |
Jim Page
|
|
|
Hydrostatic test witnessed for southeast wet standpipe, levels 2, 3 and 5, no pressure observed at contractor supplied gauges. Level 4 still needs to have hydro completed.
|
INSP-Sprinkler Rough-in | 10/27/2017 | 10/30/2017 | 10/30/2017 | A | DONE |
Troy Cobbley
|
|
|
Duplicate inspection work an inspection I performed on Fridayl.
Tenting of sprinkler lines in units 509-519 passed. Numerous corrections made while I was on site.
|
INSP-Sprinkler Rough-in | 10/27/2017 | 10/27/2017 | 10/27/2017 | P | PASS |
Troy Cobbley
|
|
|
Tenting of sprinkler lines in units 509-519 passed. Numerous corrections made while I was on site.
|
INSP-Sprinkler Rough-in | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | FAIL |
Jim Page
|
|
|
Overhead fire sprinkler piping is covered in numerous areas, a clear pocket must be maintained between sheetrock and fire sprinkler piping for radiant heat to reach pipe. Overehad fire sprinkler piping north of the e;evator lobby is not approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | PASS |
Jim Page
|
|
|
24 hour air test complete
|
INSP-Sprinkler Rough-in | 9/21/2017 | 9/21/2017 | 9/21/2017 | P | PART |
Jim Page
|
|
|
24 hour air test started with 50psi at 2:00pm
|
INSP-Sprinkler Rough-in | 9/7/2017 | 9/8/2017 | 9/8/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping north of elevator on level 4 complete, level 4 north of elevator approved for cover.
|
INSP-Sprinkler Rough-in | 8/29/2017 | 8/30/2017 | 8/30/2017 | A | PART |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping on the remainder of level 5 complete (North of elevator shaft) insulation/tenting still needs to be installed, cover is not approved until tenting inspection is complete.
|
INSP-Sprinkler Rough-in | 8/16/2017 | 8/17/2017 | 8/17/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting on level 5 south of the elevator shate complete, level 5 south of elevator shaft approved for cover.
|
INSP-Sprinkler Rough-in | 8/16/2017 | 8/16/2017 | 8/16/2017 | P | CANC |
Jim Page
|
|
|
Inspection request rescheduled for 17AUG2017, this request is cancelled
|
INSP-Sprinkler Rough-in | 8/9/2017 | 8/9/2017 | 8/9/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for south side of elevator lobby, level 4 overhead fire sprinkler piping/pendant heads complete, inspected area on level 4 approved for cover, north of elevator to be completed/inspected at a later date. Rough in inspection for south side level 5 complete, cover is not approved until insulation is installed over piping and passed inspection. North side of elevator on level 5 to be completed/inspected at a later date.
|
INSP-Sprinkler Rough-in | 7/27/2017 | 7/27/2017 | 7/27/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 3 complete, level 3 approved for cover.
|
INSP-Sprinkler Rough-in | 7/12/2017 | 7/13/2017 | 7/13/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping on level 2 complete, level 2 approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 6/29/2017 | 6/29/2017 | 6/29/2017 | A | PART |
Jim Page
|
|
|
Hydrostatic test for wet standpipe and parking level complete.
|
Permit Ready to Issue | | | 2/14/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/14/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/14/2017 | | 2/14/2017 | | DONE |
Brittany Hill
|
|
|
|
Plan resubmittals received | | | 2/13/2017 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 2/13/2017 | | 2/13/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 2/13/2017 | | 2/13/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/13/2017 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/27/2016 | | 9/27/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 9/27/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/27/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 9/22/2016 | | 9/22/2016 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 9/22/2016 | | FAIL |
|
|
|
|
Application received | | | 9/16/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 16 2016 11:35AM
|