INSP-Final Inspection | 4/26/2017 | 4/27/2017 | 4/27/2017 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 4/26/2017 | 4/26/2017 | 4/26/2017 | P | CANC |
Troy Cobbley
|
|
|
George, inspection is ready this AM if you can make that work. Phone #: ###-####
|
INSP-Final Inspection | 4/24/2017 | 4/25/2017 | 4/25/2017 | A | CANC |
Troy Cobbley
|
|
|
George Jess is the contact for this inspection. He is requesting a final inspection. Thank you. Phone #: ###-#### Inspection requested via web by Kay Haney
|
INSP-Final Inspection | 4/21/2017 | 4/24/2017 | 4/24/2017 | P | CANC |
Troy Cobbley
|
|
|
Water was not turned on yet. I spoke to George about my previous concerns with lack of protection in the room at the bottom of the brass pole.
|
INSP-Sprinkler Rough-in/Hydro | 3/10/2017 | 3/13/2017 | 3/13/2017 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping passed/complete
|
INSP-Sprinkler Rough-in | 2/13/2017 | 2/13/2017 | 2/13/2017 | P | PASS |
Troy Cobbley
|
|
|
2nd floor sprinkler piping is okay to cover
|
Plan Modification Accepted | | | 1/20/2017 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 1/20/2017 | | 1/20/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/20/2017 | | 1/20/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/20/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 1/20/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/20/2017 | | DONE |
|
|
|
Plan mod
|
INSP-Sprinkler Rough-in | 1/17/2017 | 1/18/2017 | 1/18/2017 | A | PART |
Troy Cobbley
|
|
|
First floor general rough-in passed with a couple of exceptions which include two additional 90's in both 4" mains close to the riser, missing seismic restraints in the Apparatus Bay and possible required coverage below the brass pole, missing seismic bracing and possible blocked heads in restrooms. The second floor rough-in could not be performed due to pipe routing changes. Plans need to be resubmitted for plan modifications. Additional cover inspections will be required when the sprinkler drops have been cut and located.
|
Permit Ready to Issue | | | 10/3/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/3/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/3/2016 | | 10/3/2016 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 9/30/2016 | | 9/30/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/30/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/28/2016 | | 9/28/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/28/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Sprinkler Plan Check | 9/21/2016 | | 9/21/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 9/21/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/21/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 9/20/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 9/20/2016 | | 9/20/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 9/16/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 16 2016 1:48PM
|