INSP-Final Inspection | 1/17/2017 | 1/17/2017 | 1/17/2017 | P | PASS |
Scott Arellano
|
|
|
Performed test and witnessed all levels successfully stop audible entertainment with full audible and visual fire alarm notification activated.
|
INSP-Final Inspection | 1/4/2017 | 1/4/2017 | 1/4/2017 | P | PART |
Jim Page
|
|
|
Partial final inspection complete for fire alarm system, city approved drawings match the installation. Need to verify audio shutdown on DJ equipment during a fire alarm event, permit cannot be finaled until audio shutdown is inspected and passed.
|
INSP-Final Inspection | 12/29/2016 | 12/30/2016 | 12/30/2016 | A | FAIL |
Jim Page
|
|
|
Audio visual devices tested and inspected, all tested correctly. On-site city approved drawings do not match the system installed, approved drawings show numerous smoke detectors throughout space and the smoke detectors have been reomved. A city approved drawing needs to be provided showing the removal of the devices or the system will need to match what was submitted.
|
CHANGE STATUS TO (ISS) | | | 11/18/2016 | | DONE |
|
|
|
|
Plan resubmittals received | | | 11/17/2016 | | DONE |
|
|
|
Plan modification showing all changes.
|
CHANGE STATUS TO (REV) | | | 11/17/2016 | | DONE |
|
|
|
|
1st review completed | | | 11/17/2016 | | PASS |
|
|
|
|
Alarm Plan Check | 11/17/2016 | | 11/17/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/17/2016 | | DONE |
|
|
|
Resubmittal of plan modification approved. No additional review comments.
|
Permit Ready to Issue | | | 10/20/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/20/2016 | | |
|
|
|
|
Inspection Record Card- Fire | 10/20/2016 | | 10/20/2016 | | DONE |
Christina Prado
|
|
|
|
Miscellaneous action | | | 9/29/2016 | | DONE |
|
|
|
Email from Kenny: Thank you for the confirmation Lee. I received approval from Tom Gainer to remove the door holders on the 3 doors in the stairway. Therefore, we will resubmit showing those and their smoke detectors removed. We will also be removing the pull stations, adding one by the riser, and moving the elevator smokes over about 8-10 feet as we discussed.
|
Telephone call | | | 9/28/2016 | | DONE |
|
|
|
Kenny called to see if manual pull stations were required. I informed him that since it is fully sprinklered, only one was required and that if the owner would rather not have them, they could be excluded. This would require updated as built drawings at the time of completion.
|
Alarm Plan Check | 9/28/2016 | | 9/28/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 9/28/2016 | | DONE |
|
|
|
Plans approved with review comments and requirements.
|
Plan resubmittals received | | | 9/26/2016 | | DONE |
|
|
|
|
1st review completed | | | 9/23/2016 | | FAIL |
|
|
|
Notification inadequate, heat substituted for a required smoke, notification product datat missing. See review comments.
|
Miscellaneous action | | | 9/23/2016 | | DONE |
|
|
|
Emailed Kenny to also let him know that the existing sound systems will be required to have a shunt interface to stop or reduce ambient background sound levels.
|
Plan assigned to (Lee) | 9/22/2016 | | 9/22/2016 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 9/22/2016 | | DONE |
|
|
|
Failed on pre-screen review. Kenny was directed to seperate drawings into individual files.
|
Application received | | | 9/19/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 19 2016 10:16AM
|