INSP-Final Inspection | 12/4/2017 | 12/4/2017 | 12/4/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for building 2 passed/complete.
|
INSP-Final Inspection | 11/21/2017 | 11/28/2017 | 11/28/2017 | P | FAIL |
Jim Page
|
|
|
1. Room 201 has exposed CPVC in water heater room. Head to close to ceiling fan. 2. Head in corridor between rooms 205 & 207 needs to be changed to an intermidate temperature, head is within 12 inches of heat register. 4. Room 213 has head to low in bathroom, same head is missing escutcheon. 5. Rooms 209, 214, 216, 220, 306, 309, and 504 has escutcheons missing. 8. Rooms 205, 219, 301, 414, 507, 516, and 519 has sprinkler heads to close to ceiling fans. 9. All exposed CPVC needs to be covered by sheetrock.
|
INSP-Sprinkler Rough-in/Hydro | 9/22/2017 | 9/22/2017 | 9/22/2017 | P | PASS |
Jim Page
|
|
|
24 hour air test complete
|
INSP-Sprinkler Rough-in | 9/21/2017 | 9/21/2017 | 9/21/2017 | P | PART |
Jim Page
|
|
|
24 hour air test started with 50psi at 2:00pm
|
INSP-Sprinkler Rough-in/Hydro | 8/28/2017 | 8/28/2017 | 8/28/2017 | P | PART |
Jim Page
|
|
|
Hydrostatic test complete for parking level dry system, levels 2, 4 and 5 wet systems. Level 3 had a visable leak, leak was repaired, system will be rechecked on 29AUG2017
|
INSP-Sprinkler Rough-in/Hydro | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | PART |
Jim Page
|
|
|
Hydrostatic test for wet standpipe complete
|
INSP-Sprinkler Rough-in | 6/21/2017 | 6/22/2017 | 6/22/2017 | A | PART |
Jim Page
|
|
|
Rough to cover inspectio for insulation above fire sprinkler piping complete, level 5 approved for cover.
|
INSP-Sprinkler Rough-in | 6/13/2017 | 6/13/2017 | 6/13/2017 | P | PART |
Jim Page
|
|
|
Corrections have been made in rooms where too many heads were installed of off 1 inch pipe (see city approved drawings where rooms were noted with yellow highlighter and red ink indicating no cover) Rooms that were noted are approved for cover. North side of elevator lobby level 5 has been inspected, piping cannot be covered until an inspection has been performed to verify that there is a clear pocket between the sheetrock and overhead fire sprinkler piping/insulation for freeze prevention.
|
INSP-Supply line flush | 6/7/2017 | 6/9/2017 | 6/9/2017 | A | CANC |
Jim Page
|
|
|
This inspection request cancelled, request is for underground flush and notes need to be entered under FIR16-00473
|
INSP-Sprinkler Rough-in | 6/8/2017 | 6/8/2017 | 6/8/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete, notated city approved drawings with yellow highlighter/red ink area's approved for cover, also have area's notated on city approved drawings with yellow highlighter/red ink rooms that are not approved for cover due to pipe install not matching city approved drawings (to many heads off of 1 inch pipe)
|
INSP-Supply line flush | 5/31/2017 | 6/1/2017 | 6/1/2017 | A | CANC |
Jim Page
|
|
|
Cancelled per point of contact, Paul Phone #: ###-####, will be rescheduled.
|
INSP-Sprinkler Rough-in | 5/17/2017 | 5/17/2017 | 5/17/2017 | P | PART |
Jim Page
|
|
|
Rough to cover inspection complete for overhead fire sprinkler piping located east of the elevator lobby on level 2, all of level 2 approved for cover.
|
INSP-Sprinkler Rough-in | 4/24/2017 | 4/25/2017 | 4/25/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for overhead fire sprinkler piping on level 3, notated city approved drawings with green highlighter/red ink area's approved for cover.
|
INSP-Sprinkler Rough-in | 4/19/2017 | 4/20/2017 | 4/20/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for overhead fire sprinkler piping located on level 4, notated city approved drawings with pink highlighter/red ink area's approved for cover.
|
INSP-Sprinkler Rough-in | 4/12/2017 | 4/13/2017 | 4/13/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for overhead fire sprinkler piping on level 2 complete, notated city approved drawings with green highlighter/red ink area's approved for cover on level 2. Partial rough to cover for overhead fire sprinkler piping/tenting on level 5 complete, notated city approved drawings with green highlighter/red ink area's approved for cover on level 5.
|
INSP-Sprinkler Rough-in | 4/5/2017 | 4/5/2017 | 4/5/2017 | P | CANC |
Jim Page
|
|
|
Incorrect permit for inspection request, (Inspection request is for tenting associated with FIR16-00607, building 3 clubhouse) this request is cancelled and an inspection request will be generated for the correct permit number.
|
INSP-Sprinkler Rough-in/Hydro | 3/27/2017 | 3/27/2017 | 3/27/2017 | P | FAIL |
Jim Page
|
|
|
Rough in inspection for level 2 corridor main complete. Rough to cover inspection performed on level 4, pipe scheduling did not match the city approved drawings, stopped inspection after finding 5 locations with too many heads off of 1 inch pipe. Pipe scheduling will need to be changed to coincide with city approve drawings, piping cannot be covered until repairs are made and a re-inspection is performed
|
INSP-Sprinkler Rough-in | 3/21/2017 | 3/23/2017 | 3/23/2017 | A | CANC |
Jim Page
|
|
|
Called point of contact at phone number provided, Carlos Phone #: ###-#### three times to coordinate a meeting place, left a message on the first attempt, no return call recieved by 12:10pm, this request is cancelled, contractor will need to reschedule.
|
Sprinkler Plan Check | 3/20/2017 | | 3/20/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/20/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/20/2017 | | DONE |
|
|
|
plan mod ONLY
|
CHANGE STATUS TO (ISS) | | | 3/20/2017 | | DONE |
|
|
|
plan mod ONLY - no fees due
|
INSP-Sprinkler Rough-in | 3/14/2017 | 3/15/2017 | 3/15/2017 | P | FAIL |
Jim Page
|
|
|
Approved plans that were provided were not the correct levels needing to be inspected, inspection request will need to reschedule when correct set of approved drawings can be provided.
|
INSP-Sprinkler Rough-in | 3/6/2017 | 3/6/2017 | 3/6/2017 | P | PART |
Jim Page
|
|
|
Partial rough in inspection for overhead fire sprinkler piping located on level 5 complete, notated plans that were on site with yellow highlighter/red ink, area's that were inspected. Need to have a city approved set of drawings on site for next inspection. Piping in attic spaces cannot be covered until tenting is installed, inspected and passed, any piping that is covered before tenting inspection will have cover material removed to verify tenting installation.
|
Sprinkler Plan Check | 10/14/2016 | | 10/14/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/14/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/14/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/14/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/14/2016 | | 10/14/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Sprinkler Plan Check | 9/30/2016 | | 9/30/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 9/30/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/30/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 9/29/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 9/29/2016 | | 9/29/2016 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/29/2016 | | DONE |
|
|
|
as per Tim Frost changed address from 2950 E Parkcenter Blvd (S0919336030) to 2972 E Parkcenter Blvd
|
Application received | | | 9/23/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 23 2016 8:32AM
|