Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberFIR16-00607
StatusFinaled
Name DELTA FIRE SYSTEMS
Site Address 2950 E PARKCENTER BLVD
Project NameArboretum at Barber Station #3
Customer Number 
ePlanReviewYes
Description
[Arboretum at Barber Station Building #3]
The fire sprinkler scope of work consists of Building #3 only. The two level building is protected per NFPA 13. The 4” underground will supply a 2 ½” backflow. The bottom level has various ordinary hazard areas. The top level has apartments and utilizes residential sprinklers. The building has floor level control valves. The top level is tented.

The underground piping is under permit FIR16-00473

• Exposed piping is steel. Concealed branch line piping on floor 1-2 is CPVC, the mains are steel.

[BLD16-01060] - (Building #3) Permit to construct a new 14,850 square foot (2) story apartment / clubhouse. The first floor is about 7,635 square feet and the second floor is 7,215 square feet. This building is fully fire sprinklered with an NFPA 13 system to comply corridor reduction requirements. Scope of work includes: construct a new concrete foundation, construction of wood frame 2 story building, installation of interior non-bearing walls and bearing walls to create 6 individual units, new plumbing, new electrical, new mechanical, new insulation, new windows, new doors, and interior finishes in compliance with Chapter 8 of the 2012 IBC. This building will be sprinklered with a fully compliant NFPA 13 system to comply corridor exceptions. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/18/20177/19/20177/19/2017PPASS
DetailsJim Page
Final fire sprinkler inspection for this permit passed/complete
INSP-Final Inspection7/6/20177/7/20177/6/2017ACANC
DetailsJim Page
Called point of contact listed, Paul Phone #: ###-####, Installing contractor did not schedule fire sprinkler inspection, inspection for fire sprinklers will not be perfromed if FIR permit is called in by anyone other than the installing contractor.
INSP-Sprinkler Rough-in/Hydro6/29/20176/29/20176/29/2017APASS
DetailsJim Page
Hydrostatic test for overhead fire sprinkler piping complete
INSP-Supply line flush5/31/20176/1/20176/1/2017ACANC
DetailsJim Page
Cancelled per point of contact, Paul Phone #: ###-####, will be rescheduled.
INSP-Sprinkler Rough-in5/25/20175/25/20175/25/2017APART
DetailsJim Page
Rough to cover inspection for overhead fire sprinkler piping/pendant heads located above hardlids complete, approved for cover.
INSP-Conference5/24/20175/25/20175/25/2017PDONE
DetailsJim Page
Fire conference complete
INSP-Sprinkler Rough-in4/5/20174/5/20174/5/2017PFAIL
DetailsJim Page
Tenting is not complete, no insulation installed over piping in numerous area's. City approved drawings show a detail with attic space being completely filled with insulation, numerous area's have 6 plus inches of combustible material exposed, insulation needs to fill any and all area's in attic space or upright head protection will be required, refer to note number 8 of fire sprinkler permit review comments for specifics.
INSP-Conference3/10/20173/13/20173/13/2017PPART
DetailsJim Page
Inspection request was for a rough to cover inspection for an area on level 1 clubhouse, notated city approved drawings with red ink area approved for cover.
Sprinkler Plan Check2/22/2017 2/22/2017 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  2/22/2017 DONE
DetailsTim Frost
Permit Ready to Issue  2/22/2017 DONE
Issue and Print Permit  2/22/2017 DONE
Inspection Record Card- Fire2/22/2017 2/22/2017 DONE
DetailsBrittany Hill
Sprinkler Plan Check10/4/2016 10/4/2016 FAIL
DetailsTim Frost
1st review completed  10/4/2016 FAIL
DetailsTim Frost
Miscellaneous action  10/4/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Intake Approval  10/3/2016 PASS
Plan assigned to (Tim)10/3/2016 10/3/2016 DONE
DetailsTim Frost
Application received  9/23/2016 DONE
Application submitted via PDS Online on Sep 23 2016 8:54AM