Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR16-00616
StatusFinaled
Name SIEMENS INDUSTRY INC
Site Address 400 S CAPITOL BLVD
Project NameResidence Inn by Marrott
Customer Number 
ePlanReviewYes
Description
New Fire Alarm System Installation with area detection, elevator recall, voice evacuation system, duct detection, sprinkler monitoring, fire pump and smoke control panel. Associated with building permit BLD15-03489.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/19/20181/19/20181/19/2018PPASS
DetailsJim Page
Final fire alarm inspection complete.
INSP-Final Inspection10/2/201710/3/201710/3/2017PCANC
DetailsJim Page
Mike-high rise Phone #: ###-####
INSP-Final Inspection10/2/201710/3/201710/3/2017APART
DetailsJim Page
Final fire alarm inspection passed/complete, fire alarm permit will remain in issued status until project is complete.
INSP-Final Inspection10/2/201710/2/201710/2/2017PCANC
DetailsJim Page
Mike Phone #: ###-####-high rise
INSP-Alarm Testing9/28/20179/29/20179/29/2017PDONE
DetailsJim Page
Alarm testing complete for today.
INSP-Alarm Testing9/28/20179/29/20179/29/2017ADONE
DetailsJim Page
Alarm testing complete for the day.
INSP-Alarm Testing9/27/20179/28/20179/28/2017PDONE
DetailsJim Page
Alarm testing complete for the day.
INSP-Alarm Testing9/27/20179/28/20179/28/2017ADONE
DetailsJim Page
Fire alarm testing complete for today, audio/visual notification complete for level 1 to include parking, level 2 parking and level 3 corridor/rooms. Stairwell pressurization to include elevator shaft pressurization complete. Room notification complete for levels 3 and 10. Visual notification will be added to the 2 balconies off of the level 3 conference room on the northwest corner.
INSP-Alarm Testing9/26/20179/27/20179/27/2017PDONE
DetailsJim Page
Alarm testing complete for today
INSP-Alarm Testing9/26/20179/27/20179/27/2017APART
DetailsJim Page
Fire alarm testing complete for audio visual notification on general alarm for levels 3, 4, 5, 6 and 10. Sounder bases for resident rooms on level 3 and 10 to be tested at a later date. Testing complete for valves tampers and fire pump monitoring. Dry system to be tested at a later date. Need to test stairwell pressurization on auto function as well as floor smoke control.
INSP-Final Inspection9/25/20179/26/20179/26/2017APART
DetailsJim Page
Final inspection complete for level 9, 8, and 7, remaining levels to be tested at a later date.
INSP-Alarm Testing9/13/20179/13/20179/13/2017PDONE
DetailsJim Page
Fire alarm testing complete for today.
Miscellaneous action  7/28/2017 DONE
Geoff Weeks requested the workflow be reopened for a plan modification. Some penthouse areas are being changed to non accessible areas and he wants to remove previously required drtection and notification. Eplanreview work flor was reopened to allow for a plan modification upload.
Telephone call  5/8/2017 DONE
Geoffry Weeks called to discuss acceptance testing proceedures. Want to test a full floor per week with final tests as required bu the inspector. I informed him that we could work with this schedule but stressed the importance of pre-testing and being prepared for each test. I let him know that Jim Page would be his inspector for most, if not all of the tests. Also informed him that he needs to call the permit desk the day prior to his choice of days. I made him aware that we would not be able to schedule full days of testing and that if he needs to get a complete floor done each week that he may want to try to schedule Tuesdays or Wednesdays to allow time to make any corrections that may come up.
Meeting  3/2/2017 DONE
PDS office meeting with owners rep Dave Kadanko to discuss strobe placement. Siemens design for strobe placement in hearing impaired rooms did not take window curtains into account. Current placement would allow the curtains to be drawn over the strobes. It was agreed that the curtains are to be installed in a manner that prevents them from covering the strobes by installing stops in the curtain tracks. Inspector to verify during acceptance tests.
Permit Ready to Issue  11/1/2016 DONE
NEED Fire Contractor
Issue and Print Permit  11/1/2016 DONE
Inspection Record Card- Fire11/1/2016 11/1/2016 DONE
DetailsKristal Soland
Alarm Plan Check10/28/2016 10/28/2016 PASS
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  10/28/2016 DONE
Plans approved with review comments.
Plan resubmittals received  10/27/2016 DONE
1st review completed  10/12/2016 FAIL
See 1st review comment notes.
Miscellaneous action  10/12/2016 DONE
Emailed review comments to Geoff Weeks.
Plan assigned to (Lee)10/10/2016 10/10/2016 DONE
DetailsLee G Meredith
Miscellaneous action  9/29/2016 DONE
Failed pre-screen review. Missing 601 checklist and all 23 drawings were submitted as a single file of 15MB. Emailed Geoff detailing required changes. Corrections were made and resubmitted on the same day. I informed Geoff that I would not be able to start my review untill Oct. 10th. He indicated that they would not have any site work untill next spring and that this was not a problem.
Application received  9/28/2016 DONE
Application submitted via PDS Online on Sep 28 2016 2:46PM