INSP-Final Inspection | 2/6/2017 | 2/7/2017 | 2/7/2017 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 2/2/2017 | 2/3/2017 | 2/3/2017 | A | PASS |
Troy Cobbley
|
|
|
City pressure hydro on the hole system passed.
|
INSP-Sprinkler Rough-in | 1/30/2017 | 1/31/2017 | 1/31/2017 | A | PART |
Troy Cobbley
|
|
|
Remaining piping can be covered. High temp heads need to be installed infront of the unit heaters as per table 8.3.2.5(a)
|
INSP-Sprinkler Rough-in | 1/20/2017 | 1/23/2017 | 1/23/2017 | P | PASS |
Troy Cobbley
|
|
|
Second floor rough-in passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 1/17/2017 | 1/18/2017 | 1/18/2017 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro for the under mezzanine piping passed. Previous corrections done except for the seismic bracing in the corridor.
|
INSP-Sprinkler Rough-in | 1/16/2017 | 1/17/2017 | 1/17/2017 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where sprinkler piping on the first floor is ok to cover. Also see acouple of locations where minor corrections are needed.
|
INSP-Sprinkler Rough-in | 11/30/2016 | 11/30/2016 | 11/30/2016 | P | PASS |
Troy Cobbley
|
|
|
Piping above the hardlid next to the elevator as marked on the plans is ok to cover.
|
Intake Approval | | | 10/13/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/13/2016 | | 10/13/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/13/2016 | | 10/13/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/13/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/13/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/13/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/13/2016 | | 10/13/2016 | | DONE |
Kristal Soland
|
|
|
|
Application received | | | 10/11/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 11 2016 1:44PM
|