INSP-Final Inspection | 12/1/2016 | 12/1/2016 | 12/1/2016 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 11/30/2016 | 12/1/2016 | 12/1/2016 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 11/29/2016 | 11/30/2016 | 11/30/2016 | A | FAIL |
Troy Cobbley
|
|
|
Contact plan review to see if as-builts or plan modifications are required for the new strobe and changes in the candellas of the other strobes, provide strobe coverage in the rear exit area, provide immediate shut down of the hvac units per the IMC, provide record of completion forms.
|
Permit Ready to Issue | | | 10/17/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/17/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/17/2016 | | 10/17/2016 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 10/14/2016 | | 10/14/2016 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 10/14/2016 | | FAIL |
|
|
|
Strobe candela inadequate for indicated ceiling height.
|
Telephone call | | | 10/14/2016 | | DONE |
|
|
|
Josiah called to say the general contractor informed him that finished ceiling heights are actually 10 feet above finished floor and not 14 as indicated on the application. I told him to note this on the drawing and resubmit.
|
Plan resubmittals received | | | 10/14/2016 | | DONE |
|
|
|
|
Alarm Plan Check | 10/14/2016 | | 10/14/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/14/2016 | | DONE |
|
|
|
Resubmittal approved with review comments.
|
Application received | | | 10/13/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 13 2016 1:53PM
|