INSP-Final Inspection | 12/21/2016 | 12/22/2016 | 12/22/2016 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 12/20/2016 | 12/20/2016 | 12/20/2016 | P | FAIL |
Troy Cobbley
|
|
|
Not all of the work is complete due to no access to rooms due to flooring being installed
|
INSP-Sprinkler Rough-in | 12/9/2016 | 12/12/2016 | 12/12/2016 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered
|
INSP-Sprinkler Rough-in | 11/16/2016 | 11/17/2016 | 11/17/2016 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations of piping inspected and where piping is ok to cover.
|
Intake Approval | | | 10/24/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/24/2016 | | 10/24/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/24/2016 | | 10/24/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/24/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/24/2016 | | DONE |
Tim Frost
|
|
|
|
Override - Parcel Holds | | | 10/24/2016 | | |
|
|
|
|
Permit Ready to Issue | | | 10/24/2016 | | DONE |
|
|
|
all requirments met
|
Override - Parcel Holds | | | 10/24/2016 | | |
|
|
|
|
Issue and Print Permit | | | 10/24/2016 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 10/24/2016 | | |
|
|
|
|
Inspection Record Card- Fire | 10/24/2016 | | 10/24/2016 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 10/21/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 21 2016 4:23PM
|