INSP-Final Inspection | 5/14/2018 | 5/15/2018 | 5/15/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in/Hydro | 5/3/2018 | 5/4/2018 | 5/4/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping witnessed, no pressure loss observed at riser provided gauge.
Phone #: ###-#### Inspection requested via web by Sam Ball
|
INSP-Sprinkler Rough-in | 10/5/2017 | 10/6/2017 | 10/6/2017 | P | PASS |
Jim Page
|
|
|
Rough to ocver inspection for overhead fire sprinkler piping/tenting complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2017 | 10/5/2017 | 10/5/2017 | P | PASS |
Jim Page
|
|
|
Hydrostatic test complete for overhead fire sprinkler piping.
|
INSP-Supply line flush | 7/25/2017 | 7/26/2017 | 7/26/2017 | P | DONE |
Jim Page
|
|
|
Underground main supply flush complete.
|
INSP-Sprinkler Rough-in | 6/1/2017 | 6/1/2017 | 6/1/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete
|
Permit Ready to Issue | | | 10/31/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/31/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/31/2016 | | 10/31/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 10/28/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/28/2016 | | 10/28/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/28/2016 | | 10/28/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/28/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/24/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 24 2016 8:36AM
|