INSP-Final Inspection | 5/25/2017 | 5/25/2017 | 5/25/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in | 5/3/2017 | 5/3/2017 | 5/3/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/pendant heads in area of work complete, area of work approved for cover.
|
INSP-Sprinkler Rough-in | 4/13/2017 | 4/13/2017 | 4/13/2017 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping above the two restrooms is ok to cover.
|
Plan Modification Accepted | | | 4/11/2017 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 4/11/2017 | | 4/11/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/11/2017 | | 4/11/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/11/2017 | | DONE |
|
|
|
plan mod fees paid
|
CHANGE STATUS TO (ISS) | | | 4/11/2017 | | DONE |
|
|
|
plan mod fees paid
|
Intake Approval | | | 10/26/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/26/2016 | | 10/26/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/26/2016 | | 10/26/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/26/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/26/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/26/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/26/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/26/2016 | | 10/26/2016 | | DONE |
Brittany Hill
|
|
|
|
Application received | | | 10/25/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 25 2016 11:02AM
|