INSP-Final Inspection | 4/25/2018 | 4/30/2018 | 4/30/2018 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
|
INSP-Sprinkler Rough-in/Hydro | 8/10/2017 | 8/10/2017 | 8/10/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping and tenting complete, approved for cover. Hydrostatic test for overhead fire sprinkler piping complete.
|
INSP-Supply line flush | 7/25/2017 | 7/26/2017 | 7/26/2017 | P | DONE |
Jim Page
|
|
|
Underground main supply flush complete.
|
INSP-Sprinkler Rough-in | 4/26/2017 | 4/27/2017 | 4/27/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
Permit Ready to Issue | | | 11/4/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/4/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/4/2016 | | 11/4/2016 | | DONE |
Kristal Soland
|
|
|
|
Intake Approval | | | 11/2/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/2/2016 | | 11/2/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/2/2016 | | 11/2/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 11/2/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/2/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/29/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 29 2016 12:06PM
|