Permit Information
Permit NumberFIR16-00701
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 8000 S FEDERAL WAY
Project NameMicron Bldg 51
Customer NumberUDG ONLY
ePlanReviewYes
Description
[Micron Building 51 - C24074 UDG only]
The fire sprinkler scope of work consists of four underground connections to riser rooms for a new building. Most of the underground piping is 10” A combination of yard PIV and wall PIV are being utilized,

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.

[BLD16-01184] - (MICRON - Bldg 51) Permit to construct the steel super structure to a new 168,000 square foot R & D Facility. This permit scope of work was only for the structural steel construction. No details of the exterior coverings / insulation / Interior Exit stairs / etc. were provided as part of this permit. Current alternates are submitted; however, assurances were given that this project will proceed regardless of the approval of the alternates. Foundation permit issued under BLD16-01184. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/11/20197/11/20197/11/2019APASS
DetailsJim Page
Final inspection for undergorund supply has been completed.
INSP-Sprinkler Rough-in/Hydro7/11/20197/11/20197/11/2019PDONE
DetailsJim Page
Underground hydrostatic test has been witnessed, no pressure loss was observed.

Clearnce Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro7/11/20197/11/20197/11/2019ACANC
DetailsJim Page
INSP-Supply line flush9/26/20179/27/20179/27/2017PDONE
DetailsJim Page
S.W. Riser Underground Flush main line flush complete
INSP-Supply line flush7/18/20177/19/20177/19/2017PDONE
DetailsJim Page
Underground main line flush for east riser room complete
INSP-Supply line flush6/26/20176/27/20176/27/2017PDONE
DetailsJim Page
Underground flush for southeast riser room complete.
INSP-Supply line flush6/26/20176/26/20176/26/2017PCANC
DetailsJim Page
1 pm flush per Micron request. Phone #: ###-#### >> Inspection requested via web by Sheldon Gray Inspection cancelled from web by: Sheldon Gray
INSP-Supply line flush5/2/20175/4/20175/4/2017APART
DetailsJim Page
N.W. Underground Flush complete
INSP-Sprinkler Rough-in3/28/20173/29/20173/29/2017PPART
DetailsJim Page
Partial rough to cover inspection complete for south east underground, approved for cover.
INSP-Sprinkler Rough-in2/24/20172/24/20172/24/2017PPART
DetailsJim Page
Partial rough to cover inspection complete for underground supply, notated city approved drawings area's approved for cover.
INSP-Sprinkler Rough-in2/22/20172/22/20172/22/2017PPART
DetailsJim Page
Partial rough to cover for underground supply complete, notated the city approved drawings with red ink area's approved for cover.
INSP-Sprinkler Rough-in2/2/20172/2/20172/2/2017PPART
DetailsJim Page
Partial cover approved for Northeast underground, notated city approved drawings area approved for cover.
Fees Due Hold12/1/2016 12/8/2016 DONE
DetailsChristina Prado
Permit Ready to Issue  11/30/2016 DONE
Issue and Print Permit  11/30/2016 DONE
Inspection Record Card- Fire11/30/2016 11/30/2016 DONE
DetailsChristina Prado
Sprinkler Plan Check11/18/2016 11/18/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  11/18/2016 DONE
DetailsTim Frost
Intake Approval  11/2/2016 PASS
Plan assigned to (Tim)11/2/2016 11/2/2016 DONE
DetailsTim Frost
Sprinkler Plan Check11/2/2016 11/2/2016 FAIL
DetailsTim Frost
1st review completed  11/2/2016 FAIL
DetailsTim Frost
Miscellaneous action  11/2/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  11/1/2016 DONE
Application submitted via PDS Online on Nov 1 2016 9:23AM