INSP-Final Inspection | 7/11/2019 | 7/11/2019 | 7/11/2019 | A | PASS |
Jim Page
|
|
|
Final inspection for undergorund supply has been completed.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | DONE |
Jim Page
|
|
|
Underground hydrostatic test has been witnessed, no pressure loss was observed.
Clearnce Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2019 | 7/11/2019 | 7/11/2019 | A | CANC |
Jim Page
|
|
|
|
INSP-Supply line flush | 9/26/2017 | 9/27/2017 | 9/27/2017 | P | DONE |
Jim Page
|
|
|
S.W. Riser Underground Flush main line flush complete
|
INSP-Supply line flush | 7/18/2017 | 7/19/2017 | 7/19/2017 | P | DONE |
Jim Page
|
|
|
Underground main line flush for east riser room complete
|
INSP-Supply line flush | 6/26/2017 | 6/27/2017 | 6/27/2017 | P | DONE |
Jim Page
|
|
|
Underground flush for southeast riser room complete.
|
INSP-Supply line flush | 6/26/2017 | 6/26/2017 | 6/26/2017 | P | CANC |
Jim Page
|
|
|
1 pm flush per Micron request. Phone #: ###-#### >> Inspection requested via web by Sheldon Gray Inspection cancelled from web by: Sheldon Gray
|
INSP-Supply line flush | 5/2/2017 | 5/4/2017 | 5/4/2017 | A | PART |
Jim Page
|
|
|
N.W. Underground Flush complete
|
INSP-Sprinkler Rough-in | 3/28/2017 | 3/29/2017 | 3/29/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for south east underground, approved for cover.
|
INSP-Sprinkler Rough-in | 2/24/2017 | 2/24/2017 | 2/24/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover inspection complete for underground supply, notated city approved drawings area's approved for cover.
|
INSP-Sprinkler Rough-in | 2/22/2017 | 2/22/2017 | 2/22/2017 | P | PART |
Jim Page
|
|
|
Partial rough to cover for underground supply complete, notated the city approved drawings with red ink area's approved for cover.
|
INSP-Sprinkler Rough-in | 2/2/2017 | 2/2/2017 | 2/2/2017 | P | PART |
Jim Page
|
|
|
Partial cover approved for Northeast underground, notated city approved drawings area approved for cover.
|
Fees Due Hold | 12/1/2016 | | 12/8/2016 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 11/30/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/30/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/30/2016 | | 11/30/2016 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 11/18/2016 | | 11/18/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/18/2016 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 11/2/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/2/2016 | | 11/2/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/2/2016 | | 11/2/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 11/2/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 11/2/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 11/1/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 1 2016 9:23AM
|