Permit Information
Permit NumberFIR16-00704
StatusFinaled
Name STATEFIRE DC SPECIALTIES
Site Address 2800 S LIBERTY ST
Project NameCity of Boise UM Garage Exp
Customer Number 
ePlanReviewYes
Description
[City of Boise UM Garage Expansion]
The fire sprinkler scope of work consists of connecting to an existing 4” outlet. Running a new 4” main
in a tree system to 2” branch lines. The calculation area was increased for roof slope and dry system.
[BLD16-02141] - Expansion of existing CMU maintenance garage to include new CMU walls, lighting,
radiant heaters, and coiling oh doors. This building is fire sprinklered. **TLW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/17/20171/18/20171/17/2017PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro1/16/20171/17/20171/17/2017APASS
DetailsTroy Cobbley
200 lb overhead hydro test passed
INSP-Final Inspection1/12/20171/13/20171/13/2017PFAIL
DetailsTroy Cobbley
Not ready for a final yet still need the 2 hour hydro test and reconnection to the main system. The 24 hour air test passed
Sprinkler Plan Check1/13/2017 1/13/2017 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  1/13/2017 DONE
DetailsTim Frost
CHANGE STATUS TO (ISS)  1/13/2017 DONE
Permit Ready to Issue  1/13/2017 DONE
plan mod ONLY - Do NOT re-issue
CHANGE STATUS TO (ISS)  1/13/2017 DONE
as per Tim Frost no fee due
INSP-Sprinkler Rough-in/Hydro1/11/20171/12/20171/12/2017PPART
DetailsTroy Cobbley
Rough-in Inspection passed with the seismic brace added. Started the 24hr Air test at 2:00pm with 50 psi on the guage.
INSP-Sprinkler Rough-in1/6/20171/9/20171/9/2017APART
DetailsTroy Cobbley
Plan modifications are needed showing the six additional 90's in the 4" main and the missing long. seismic bracing needs to be installed.
Sprinkler Plan Check11/21/2016 11/21/2016 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  11/21/2016 DONE
DetailsTim Frost
CHANGE STATUS TO (ISS)  11/21/2016 DONE
Plan Modification Accepted  11/15/2016 FAIL
Plan assigned to (Tim)11/15/2016 11/15/2016 DONE
DetailsTim Frost
Permit Ready to Issue  11/10/2016 DONE
Issue and Print Permit  11/10/2016 DONE
Inspection Record Card- Fire11/10/2016 11/10/2016 DONE
DetailsBrittany Hill
Intake Approval  11/3/2016 PASS
Plan assigned to (Tim)11/3/2016 11/3/2016 DONE
DetailsTim Frost
Sprinkler Plan Check11/3/2016 11/3/2016 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  11/3/2016 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  11/3/2016 DONE
DetailsTim Frost
Application received  11/1/2016 DONE
Application submitted via PDS Online on Nov 1 2016 2:25PM