INSP-Final Inspection | 6/8/2017 | 6/9/2017 | 6/9/2017 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 5/31/2017 | 6/2/2017 | 6/2/2017 | P | FAIL |
Jim Page
|
|
|
West roof top HVAC unit would not start up to test unit shutdown upon induct smoke detector activation. Fire alarm control panel signage needs to be installed on exterior door leading to the fire panel. All other associated fire alarm components tested satisfactorily.
|
INSP-Final Inspection | 5/10/2017 | 5/12/2017 | 5/12/2017 | A | CANC |
Troy Cobbley
|
|
|
Sprinkler contractor is not ready. To be rescheduled
|
Permit Ready to Issue | | | 12/6/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/6/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/6/2016 | | 12/6/2016 | | DONE |
Brittany Hill
|
|
|
|
Alarm Plan Check | 11/29/2016 | | 11/29/2016 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/29/2016 | | DONE |
|
|
|
Plans approved with review comments.
|
1st review completed | | | 11/28/2016 | | PASS |
|
|
|
|
Miscellaneous action | | | 11/28/2016 | | DONE |
|
|
|
Failed prescreen review. Fire pump monitoring missing.
|
Plan resubmittals received | | | 11/28/2016 | | DONE |
|
|
|
|
Miscellaneous action | | | 11/28/2016 | | DONE |
|
|
|
Riser has not been updated with the added pump monitor points. Emailed Adam and requested he email the corrected drawing to me.
|
Plan resubmittals received | | | 11/18/2016 | | DONE |
|
|
|
|
Telephone call | | | 11/18/2016 | | DONE |
|
|
|
Began drawing review. Found that some information was missing. Called Adam to let him know that there are 2 sprinkler zones due to size of the building and his drawings only show one. Also, flow and tampers for the fire pump do not ssem to be monitored. Only the pump controller. Adam said he would corridnate with Tom Easton to get an accurate list of points to monitor and update the drawing.
|
Plan assigned to (Lee) | 11/15/2016 | | 11/15/2016 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 11/15/2016 | | DONE |
|
|
|
Plans returned to Adam Bayne on pre-screen review. Emailed Adam to let him know that drawings need to be individual drawings and submitted into the drawings folder.
|
Application received | | | 11/11/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 11 2016 8:43AM
|