Description
New Strip mall with a new fire sprinkler monitoring system. With a fire pump. Associated with building permit BLD16-02176.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection6/8/20176/9/20176/9/2017APASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection5/31/20176/2/20176/2/2017PFAIL
DetailsJim Page
West roof top HVAC unit would not start up to test unit shutdown upon induct smoke detector activation. Fire alarm control panel signage needs to be installed on exterior door leading to the fire panel. All other associated fire alarm components tested satisfactorily.
INSP-Final Inspection5/10/20175/12/20175/12/2017ACANC
DetailsTroy Cobbley
Sprinkler contractor is not ready. To be rescheduled
Permit Ready to Issue  12/6/2016 DONE
Issue and Print Permit  12/6/2016 DONE
Inspection Record Card- Fire12/6/2016 12/6/2016 DONE
DetailsBrittany Hill
Alarm Plan Check11/29/2016 11/29/2016 PASS
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  11/29/2016 DONE
Plans approved with review comments.
1st review completed  11/28/2016 PASS
Miscellaneous action  11/28/2016 DONE
Failed prescreen review. Fire pump monitoring missing.
Plan resubmittals received  11/28/2016 DONE
Miscellaneous action  11/28/2016 DONE
Riser has not been updated with the added pump monitor points. Emailed Adam and requested he email the corrected drawing to me.
Plan resubmittals received  11/18/2016 DONE
Telephone call  11/18/2016 DONE
Began drawing review. Found that some information was missing. Called Adam to let him know that there are 2 sprinkler zones due to size of the building and his drawings only show one. Also, flow and tampers for the fire pump do not ssem to be monitored. Only the pump controller. Adam said he would corridnate with Tom Easton to get an accurate list of points to monitor and update the drawing.
Plan assigned to (Lee)11/15/2016 11/15/2016 DONE
DetailsLee G Meredith
Miscellaneous action  11/15/2016 DONE
Plans returned to Adam Bayne on pre-screen review. Emailed Adam to let him know that drawings need to be individual drawings and submitted into the drawings folder.
Application received  11/11/2016 DONE
Application submitted via PDS Online on Nov 11 2016 8:43AM