INSP-Final Inspection | 3/1/2018 | 3/1/2018 | 3/1/2018 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Supply line flush | 2/27/2018 | 2/28/2018 | 2/28/2018 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passsed
|
INSP-Supply line flush | 2/22/2018 | 2/23/2018 | 2/23/2018 | A | FAIL |
Jim Page
|
|
|
Contractor could not get in touch with water purveyor, flush will need to be rescheduled.
|
INSP-Sprinkler Rough-in/Hydro | 2/23/2018 | 2/23/2018 | 2/23/2018 | A | DONE |
Jim Page
|
|
|
Underground hydrostatic test witnessed, no pressure loss observed at underground supply pressure gauge.
|
INSP-Sprinkler Rough-in/Hydro | 5/5/2017 | 5/5/2017 | 5/5/2017 | P | PASS |
Scott Arellano
|
|
|
Thrust Block inspection passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/16/2016 | 12/16/2016 | 12/16/2016 | P | PASS |
Katie Marron
|
|
|
UDG inspection from tap to 5' from foundation ok to cover. Thrust blocks were in place.
Will need to inspect stub up
|
INSP-Sprinkler Rough-in/Hydro | 12/15/2016 | 12/15/2016 | 12/15/2016 | P | NR |
Katie Marron
|
|
|
|
Sprinkler Plan Check | 12/12/2016 | | 12/13/2016 | | PASS |
Scott Arellano
|
|
|
No separate comments attached to plans.
|
1st review completed | | | 12/13/2016 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2016 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/13/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/13/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/13/2016 | | 12/13/2016 | | DONE |
Kristal Soland
|
|
|
|
Plan assigned to (Scott) | 12/12/2016 | | 12/12/2016 | | DONE |
Scott Arellano
|
|
|
|
Application received | | | 12/8/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 8 2016 3:23PM
|