INSP-Final Inspection | 10/2/2017 | 10/4/2017 | 10/4/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in | 6/23/2017 | 6/23/2017 | 6/23/2017 | P | PASS |
Jim Page
|
|
|
Tenting inspection complete, overhead fire sprinkler piping approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 6/6/2017 | 6/8/2017 | 6/8/2017 | A | PART |
Jim Page
|
|
|
Rough in inspection complete, piping in attic spaces cannot be covered until tenting inspection is complete and passed, all other piping approved for cover. Hydrostatic test for overhead fire sprinkler piping complete.
|
INSP-Supply line flush | 6/6/2017 | 6/7/2017 | 6/7/2017 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
CHANGE STATUS TO (ISS) | | | 5/9/2017 | | DONE |
|
|
|
plan mod paid
|
Plan Modification Accepted | | | 4/18/2017 | | DONE |
|
|
|
Changed the brand of sprinklers
|
Sprinkler Plan Check | 4/18/2017 | | 4/18/2017 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/18/2017 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 3/8/2017 | 3/8/2017 | 3/8/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
Permit Ready to Issue | | | 2/14/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/14/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/14/2017 | | 2/14/2017 | | DONE |
Kristal Soland
|
|
|
|
Intake Approval | | | 12/28/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/28/2016 | | 12/28/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/28/2016 | | 12/28/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/28/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/28/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 12/13/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 13 2016 1:15PM
|