INSP-Final Inspection | 11/9/2017 | 11/13/2017 | 11/13/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 7/17/2017 | 7/18/2017 | 7/18/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for fire sprinkler piping/tenting complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 6/28/2017 | 6/29/2017 | 6/29/2017 | P | PASS |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping complete.
|
INSP-Supply line flush | 6/28/2017 | 6/29/2017 | 6/29/2017 | A | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
CHANGE STATUS TO (ISS) | | | 5/9/2017 | | DONE |
|
|
|
plan mod paid
|
Plan Modification Accepted | | | 4/18/2017 | | DONE |
|
|
|
Changed brand of sprinklers.
|
Sprinkler Plan Check | 4/18/2017 | | 4/18/2017 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/18/2017 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in | 3/24/2017 | 3/24/2017 | 3/24/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground supply complete, approved for cover.
|
Permit Ready to Issue | | | 2/14/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/14/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/14/2017 | | 2/14/2017 | | DONE |
Kristal Soland
|
|
|
|
Intake Approval | | | 12/28/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/28/2016 | | 12/28/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/28/2016 | | 12/28/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/28/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/28/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 12/13/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 13 2016 2:10PM
|