INSP-Final Inspection | 3/3/2017 | 3/3/2017 | 3/3/2017 | P | PASS |
Katie Marron
|
|
|
scope of work complete. permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 2/27/2017 | 2/28/2017 | 3/1/2017 | A | PASS |
Jim Page
|
|
|
Hdrostatic test for overhead fire sprinkler piping complete
|
INSP-Supply line flush | 2/16/2017 | 2/17/2017 | 2/17/2017 | P | DONE |
Jim Page
|
|
|
Underground main line flush complete
|
INSP-Supply line flush | 2/15/2017 | 2/16/2017 | 2/16/2017 | P | CANC |
Jim Page
|
|
|
Flush was not scheduled with water purveyor on day of request for flush, underground flush will need to be coordinated with contractor and water purveyor to open underground valve for flush witnessing, request for flush will need to be rescheduled to coincide with coordinated time between contractor and water purveyor.
|
INSP-Sprinkler Rough-in | 2/15/2017 | 2/16/2017 | 2/16/2017 | P | PASS |
Jim Page
|
|
|
Underground rough to cover inspection complete, approved for cover.
|
INSP-Sprinkler Rough-in | 1/17/2017 | 1/18/2017 | 1/18/2017 | A | PASS |
Katie Marron
|
|
|
Rough-in completed satisfactorily. At time of inspection tenting satisfactory. OK to cover.
|
INSP-Sprinkler Rough-in | 1/13/2017 | 1/17/2017 | 1/17/2017 | A | CANC |
Katie Marron
|
|
|
Called POC and no answer.
|
Permit Ready to Issue | | | 12/27/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/27/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/27/2016 | | 12/27/2016 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/20/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/20/2016 | | 12/20/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/20/2016 | | 12/20/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/20/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/20/2016 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 12/13/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 13 2016 3:22PM
|