INSP-Final Inspection | 7/24/2019 | 7/25/2019 | 7/25/2019 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 4/12/2019 | 4/12/2019 | 4/12/2019 | P | CANC |
Jim Page
|
|
|
Per conversation with my supervisor, Adele Schaffeld-Griffin, notes entered reading "Final fire sprinkler sign off of inspections for this permit will be completed at the same time as the life safety inspection is completed under the building permit." Please coordination with the general contractor to schedule the final inspections. Onsite inspection request for today will need to be rescheduled until coordinated inspections for the life safety can be scheduled.
Clarence Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 4/12/2019 | | DONE |
|
|
|
plan mod fee paid and plans where released.
|
Plan Modification Accepted | | | 6/19/2018 | | DONE |
|
|
|
|
Sprinkler Plan Check | 6/19/2018 | | 6/19/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/19/2018 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/19/2018 | | DONE |
|
|
|
plan mod please do not re issue
|
Plan assigned to (Tim) | 5/23/2018 | | 6/18/2018 | | DONE |
Tim Frost
|
|
|
|
Plan Modification Accepted | | | 5/23/2018 | | DONE |
Christina Prado
|
|
|
Per request from Tribal Fire
|
Plan Modification Accepted | | | 4/11/2018 | | DONE |
|
|
|
|
Intake Approval | | | 4/11/2018 | | PASS |
|
|
|
|
Sprinkler Plan Check | 4/11/2018 | | 4/11/2018 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/11/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 4/11/2018 | | DONE |
|
|
|
no charge for plan mod per Tim F.
|
INSP-Final Inspection | 6/30/2017 | 6/30/2017 | 6/30/2017 | P | PART |
Jim Page
|
|
|
Final fire sprinkler inspection for this permit is complete, permit will remain in issued status until construction for this permitted area is complete.
|
Fees Due Hold | 6/17/2017 | | 6/30/2017 | | DONE |
Christina Prado
|
|
|
|
Fees Due Hold | 6/15/2017 | | 6/16/2017 | | DONE |
Christina Prado
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 6/14/2017 | 6/15/2017 | 6/15/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete for overhead fire sprinkler piping, approved for cover. Hydrostatic test complete for overhead fire sprinklers/piping associated with this system.
|
Fees Due Hold | 5/11/2017 | | 6/14/2017 | | DONE |
Christina Prado
|
|
|
|
Permit Ready to Issue | | | 5/10/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/10/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/10/2017 | | 5/10/2017 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 5/9/2017 | | 5/9/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2017 | | DONE |
Tim Frost
|
|
|
|
Telephone call | | | 2/27/2017 | | DONE |
Tim Frost
|
|
|
Applicant working on providing letter from RDP verifying and qualifying the exclusion of fire protection in the mechanical chase and interstitial areas; as per NFPA 13-22.23.1.2.1.
|
Sprinkler Plan Check | 2/14/2017 | | 2/14/2017 | | FAIL |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 2/14/2017 | | 2/14/2017 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/14/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 12/23/2016 | | |
|
|
|
|
Plan assigned to (Tim) | 12/23/2016 | | 12/23/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/23/2016 | | 12/23/2016 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/23/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/23/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 12/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 15 2016 7:58AM
|