Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR16-00807
StatusFinaled
Name TRIBAL FIRE SYSTEMS
Site Address 8000 S FEDERAL WAY
Project NameMicron Bldg 51 System 10-6
Customer Number 
ePlanReviewYes
Description
[Micron Building 51 - System LV10-6 - C24074]
The fire sprinkler scope of work consists of providing in duct sprinkler protection for two exhaust ducts.

• The underground is under permit FIR16-00701
• Building drawings are also linked in under permit BLD16-01184 (Steel Superstructure)

Contractor’s Note:
The building permit has not been issued at this time. The building department may determine that changes are required to the building plans in order to meet code. The changes may affect the sprinkler system. The sprinkler contractor will be obligated to make all necessary changes that may be required. Therefore, if the sprinkler contractor chooses to proceed without an issued building permit, they will do so on their own cognizance. This note does not constitute an early start agreement.

[BLD16-03440] - Construction to include the building envelope to include exterior walls and roof, link construction to B36, all interior construction, doors, hardware and finishes and specialty wall, ceiling and floor materials and details, mechanical, electrical, plumbing and Fire Alarm and Fire Protection systems. Fire Protection Drawings will be a deferred submittal. Proposed Pyrophoric Room will be permitted separately.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/7/20198/7/20198/7/2019PPASS
DetailsJim Page
Final fire sprinkler inspection for area of work complete.

Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Sprinkler Rough-in8/7/20198/7/20198/7/2019PPASS
DetailsJim Page
Rough in inspection for this system has been completed.
INSP-Final Inspection7/31/20198/1/20198/1/2019ACANC
DetailsTroy Cobbley
Canceling due to manpower shortage and time constraints. Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Final Inspection7/31/20197/31/20197/31/2019PCANC
DetailsJim Page
Rescheduled for 01AUG2019 per conversation with point of contact, this request is cancelled.

Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
INSP-Final Inspection4/12/20194/12/20194/12/2019PCANC
DetailsJim Page
Per conversation with my supervisor, Adele Schaffeld-Griffin, notes entered reading "Final fire sprinkler sign off of inspections for this permit will be completed at the same time as the life safety inspection is completed under the building permit." Please coordination with the general contractor to schedule the final inspections. Onsite inspection request for today will need to be rescheduled until coordinated inspections for the life safety can be scheduled.

Clarence Phone #: ###-####
INSP-Final Inspection6/29/20176/30/20176/30/2017PPART
DetailsJim Page
Final fire sprinkler inspection for this permit is complete, permit will remain in issued status until construction for this permitted area is complete.
INSP-Sprinkler Rough-in/Hydro6/8/20176/9/20176/9/2017APASS
DetailsJim Page
Hydrostatic test for systems 10-2 and 10-6 complete.
INSP-Sprinkler Rough-in/Hydro6/8/20176/8/20176/8/2017PCANC
DetailsJim Page
Hydrostatic test cancelled by contractor, Chris ###-####
Fees Due Hold2/8/2017 3/14/2017 DONE
DetailsBrittany Hill
Permit Ready to Issue  2/7/2017 DONE
all met
Issue and Print Permit  2/7/2017 DONE
Inspection Record Card- Fire2/7/2017 2/7/2017 DONE
DetailsCarlos Velazquez
Sprinkler Plan Check2/6/2017 2/6/2017 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  2/6/2017 DONE
DetailsTim Frost
Miscellaneous action  2/6/2017 DONE
Sent Ron H and email indicating this project was approved.
Telephone call  2/2/2017 DONE
Note: Spoke with applicant 2/02/2017. The applicant indicate the ductwork which is sprinklered is sprinklered because it was combustible. The applicant indicate he did not know what is being material is being conveyed in the ductwork. I explained this information is required and the drawing cannot be approved until this information is provide.
Intake Approval  12/27/2016 PASS
Plan assigned to (Tim)12/27/2016 12/27/2016 DONE
DetailsTim Frost
Sprinkler Plan Check12/27/2016 12/27/2016 FAIL
DetailsTim Frost
1st review completed  12/27/2016 FAIL
DetailsTim Frost
Miscellaneous action  12/27/2016 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Application received  12/15/2016 DONE
Application submitted via PDS Online on Dec 15 2016 9:34AM