INSP-Final Inspection | 8/13/2019 | 8/13/2019 | 8/13/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete, plastic sheeting that was placed on sprinkler heads to protect from fire proofing was still in place in numerous locations, plastic sheeting will need to be removed before life fire safety inspection.
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2019 | 8/13/2019 | 8/13/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for this system has been witnessed, no pressure loss was observed.
|
INSP-Sprinkler Rough-in | 8/13/2019 | 8/13/2019 | 8/13/2019 | P | PASS |
Jim Page
|
|
|
Rough in inspection for this system has been completed.
|
Fees Due Hold | 6/17/2017 | | 9/13/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 6/13/2017 | | 6/16/2017 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 6/12/2017 | | 6/12/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/12/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/12/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/12/2017 | | 6/12/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 12/28/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/28/2016 | | 12/28/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/28/2016 | | 12/28/2016 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 12/28/2016 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/28/2016 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 12/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 15 2016 9:45AM
|