INSP-Final Inspection | 1/31/2019 | 2/1/2019 | 2/1/2019 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
Thanks. Call Jeff if there are questions. Phone #: ###-#### Inspection requested via web by Jeff Packham
|
INSP-Sprinkler Rough-in | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Troy Cobbley
|
|
|
The rough-in passed. This permit will be able to be finaled when the fire alarm system interconnection has been tested that Crane Alarm is installing.
Brodie Stenquist Phone #: ###-#### Inspection requested via web by Brodie Stenquist
|
INSP-Sprinkler Rough-in/Hydro | 3/30/2017 | 3/30/2017 | 3/30/2017 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
Plan Modification Accepted | | | 2/21/2017 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 2/21/2017 | | 2/21/2017 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 2/21/2017 | | PASS |
|
|
|
|
Sprinkler Plan Check | 2/21/2017 | | 2/21/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/21/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/21/2017 | | DONE |
|
|
|
please do no re issue
|
(F) Reprint permit | | | 2/21/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/21/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/21/2017 | | 2/21/2017 | | DONE |
Brittany Hill
|
|
|
|
INSP-Supply line flush | 2/16/2017 | 2/17/2017 | 2/17/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Sprinkler Rough-in | 2/16/2017 | 2/16/2017 | 2/16/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground hydo test passed. Rough-in inspection passed. Plan modifications are needed since the west sprinkler main/building layout does not match the actual conditions and this will change the hydraulic calculations.
|
INSP-Sprinkler Rough-in | 2/14/2017 | 2/14/2017 | 2/14/2017 | P | PASS |
Jim Page
|
|
|
The thrust block at the base of the IBR has been inspected and is approved for cover.
|
INSP-Sprinkler Rough-in | 2/14/2017 | 2/14/2017 | 2/14/2017 | P | PART |
Troy Cobbley
|
|
|
The underground piping on the exterior of the building is ok for cover. The thrust block at the base of the IBR has not been installed yet and will require another inspection prior to cover.
|
Intake Approval | | | 12/21/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/21/2016 | | 12/21/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/21/2016 | | 12/21/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/21/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/21/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/21/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/21/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/21/2016 | | 12/21/2016 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 12/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 15 2016 10:59AM
|