INSP-Final Inspection | 6/7/2017 | 6/7/2017 | 6/7/2017 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/4/2017 | 5/5/2017 | 5/5/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Supply line flush | 4/25/2017 | 4/26/2017 | 4/26/2017 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line flush passed
|
INSP-Sprinkler Rough-in | 3/10/2017 | 3/10/2017 | 3/10/2017 | P | PASS |
Troy Cobbley
|
|
|
The supply piping has been lowered. Underground supply piping is ok to cover.
|
INSP-Sprinkler Rough-in | 3/8/2017 | 3/9/2017 | 3/9/2017 | P | FAIL |
Troy Cobbley
|
|
|
Called contact and left voice message. Did not make contact on site. Piping does not appear to meet the minumum 4'-6" bury depth. Missing bury wire and thrust blocks. Not ready for inspeciton. I did not have plans available for inspection.
Brian Collins is the contact for this inspection. He is requesting an underground cover inspection. Thank you for your help. Phone #: ###-#### Inspection requested via web by Kay Haney
|
Intake Approval | | | 12/19/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/19/2016 | | 12/19/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/19/2016 | | 12/19/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/19/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/19/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/19/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/19/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/19/2016 | | 12/19/2016 | | DONE |
Kristal Soland
|
|
|
|
Application received | | | 12/15/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 15 2016 11:09AM
|