INSP-Final Inspection | 2/28/2017 | 2/28/2017 | 2/28/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 1/31/2017 | 2/1/2017 | 2/1/2017 | A | PASS |
Katie Marron
|
|
|
Phase 2 rough-in completed. OK to cover. Walked through new extinguisher placement, two new extinguisher to be placed.
|
INSP-Sprinkler Rough-in | 1/4/2017 | 1/5/2017 | 1/5/2017 | A | PASS |
Troy Cobbley
|
|
|
The phase 1 sprinkler piping is ok to cover. I noted one overspaced head in a office where the 9' rule is being used off of two walls which is not allowed. I will verify it has been fixed at the next inspection. Piping is ok to cover.
|
INSP-Sprinkler Rough-in | 1/4/2017 | 1/4/2017 | 1/4/2017 | P | FAIL |
Troy Cobbley
|
|
|
No inspection was performed due to signage on building door stating the building was shut due to weather
|
Application received | | | 12/30/2016 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 30 2016 12:47AM
|
Intake Approval | | | 12/30/2016 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 12/30/2016 | | 12/30/2016 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/30/2016 | | 12/30/2016 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 12/30/2016 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/2016 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/30/2016 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/30/2016 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 12/30/2016 | | 12/30/2016 | | DONE |
Brittany Hill
|
|
|
|