INSP-Final Inspection | 11/13/2017 | 11/13/2017 | 11/13/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete.
|
INSP-Final Inspection | 11/9/2017 | 11/9/2017 | 11/9/2017 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled by contractor due to flow switch issues. Inspection request will be rescheduled for later date.
|
INSP-Final Inspection | 11/8/2017 | 11/9/2017 | 11/9/2017 | A | CANC |
Jim Page
|
|
|
Coordinated for a PM inspection, this request is cancelled.
|
INSP-Final Inspection | 11/7/2017 | 11/8/2017 | 11/8/2017 | A | CANC |
Jim Page
|
|
|
Inspection request scheduled for the wrong day per conversation with point of contact, Ricky Sullivan Phone #: ###-####. This inspection request is cancelled and the correct day has been rescheduled.
|
INSP-Final Inspection | 10/16/2017 | 10/18/2017 | 10/18/2017 | A | FAIL |
Jim Page
|
|
|
Fire sprinkler head in middle level east room by stairs needs to be relocated, fire sprinkler head is currently 24 inches off of the center of the ceiling fan. Fire sprinkler head located in the west bathroom will need to be changed to an intermediate temperature head, sprinkler head is closer than 24 inches to heat source. Provide documentation showing that the spray in foam insulation is compatible with CPVC. Sheetrock needs to be installed over the exposed CPVC in the small storage room off of the garage. Irriigation was not installed at time of inspection, need to verify that the irrigation water (Irrigation water is supplied from the domestic feed) supply shuts off when flow switch activates.
|
INSP-Final Inspection | 10/16/2017 | 10/17/2017 | 10/16/2017 | A | CANC |
Jim Page
|
|
|
Ricky Sullivan is the contact for this final inspection. He would like late AM or early PM inspection time frame if possible. He would like a two hour notice. Thank you for your time. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 8/25/2017 | 8/28/2017 | 8/28/2017 | A | PASS |
Jim Page
|
|
|
Hydrostatic test for overhead fire sprinkler piping complete. Rough to cover inspection for overhead fire sprinkler piping coplete, approved for cover. Insulation is going to be spray foam type to the bottom of the roof deck, tenting not required. If spray foam comes in contact with CPVC then documentation will be required to verify compatibility of spray foam with CPVC piping.
|
INSP-Sprinkler Rough-in/Hydro | 8/23/2017 | 8/25/2017 | 8/25/2017 | A | CANC |
Troy Cobbley
|
|
|
The fitter and I could not make it to the inspection at the same time. Agreed to re-schedule for monday morning
|
Plan resubmittals received | | | 1/30/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 1/30/2017 | | 1/30/2017 | | FAIL |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/30/2017 | | 1/30/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/30/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 1/30/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/30/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/30/2017 | | 1/30/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 1/23/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/23/2017 | | 1/23/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/23/2017 | | 1/23/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 1/23/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/23/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 1/20/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 20 2017 3:56PM
|