INSP-Final Inspection | 11/6/2017 | 11/8/2017 | 11/8/2017 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work passed/complete.
|
INSP-Sprinkler Rough-in | 11/6/2017 | 11/8/2017 | 11/8/2017 | P | PASS |
Jim Page
|
|
|
Rough in inspection for area of work complete.
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2017 | 11/6/2017 | 11/6/2017 | A | CANC |
Jim Page
|
|
|
Could not connect with point of contact, Clarence Phone #: ###-####, inspection request will need to be rescheduled.
|
INSP-Final Inspection | 11/2/2017 | 11/3/2017 | 11/3/2017 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed. Did not have time to perform the rough-in
|
CHANGE STATUS TO (ISS) | | | 11/3/2017 | | DONE |
|
|
|
Per Troy ok to reopen should have been a rough in hydro not a final
|
INSP-Final Inspection | 11/1/2017 | 11/3/2017 | 11/2/2017 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sheldon Gray Inspection cancelled from web by: Jessia Maxwell
|
Fees Due Hold | 2/4/2017 | | 3/14/2017 | | DONE |
Brittany Hill
|
|
|
|
Permit Ready to Issue | | | 2/3/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/3/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/3/2017 | | 2/3/2017 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 2/1/2017 | | 2/1/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/2017 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 1/30/2017 | | FAIL |
|
|
|
This project is on hold until I know the use of the building and what will be in the building.
|
Plan assigned to (Tim) | 1/30/2017 | | 1/30/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/30/2017 | | 1/30/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 1/30/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 1/30/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 1/27/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 27 2017 10:22AM
|