INSP-Final Inspection | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Sprinkler Rough-in/Hydro | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test for this system has been witnessed, no pressure loss was observed.
|
INSP-Sprinkler Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Jim Page
|
|
|
Rough in inspection for this system has been completed.
|
INSP-Final Inspection | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | CANC |
Troy Cobbley
|
|
|
Canceling due to manpower shortage and time constraints. Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | CANC |
Jim Page
|
|
|
Rescheduled for 01AUG2019 per conversation with point of contact, this request is cancelled.
Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Sprinkler Rough-in/Hydro | 6/22/2017 | 6/23/2017 | 6/23/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection complete, approved for cover. Hydrostatic test for overhead fire sprinkler piping complete.
|
Fees Due Hold | 2/8/2017 | | 3/14/2017 | | DONE |
Brittany Hill
|
|
|
|
Sprinkler Plan Check | 2/7/2017 | | 2/7/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 2/7/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/7/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 2/7/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/7/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/7/2017 | | 2/7/2017 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 2/6/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 6 2017 9:22AM
|
Intake Approval | | | 2/6/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/6/2017 | | 2/6/2017 | | DONE |
Tim Frost
|
|
|
|