INSP-Final Inspection | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection for area of work complete.
Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Sprinkler Rough-in/Hydro | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | DONE |
Jim Page
|
|
|
Hydrostatic test has been witnessed, no pressure loss was observed.
|
INSP-Sprinkler Rough-in | 8/7/2019 | 8/7/2019 | 8/7/2019 | P | PASS |
Jim Page
|
|
|
Rough in inspection for this system has been completed.
|
INSP-Final Inspection | 7/31/2019 | 8/1/2019 | 8/1/2019 | A | CANC |
Troy Cobbley
|
|
|
Canceling due to manpower shortage and time constraints. Please call Clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | CANC |
Jim Page
|
|
|
Rescheduled for 01AUG2019 per conversation with point of contact, this request is cancelled.
Please call clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
INSP-Final Inspection | 7/31/2019 | 7/31/2019 | 7/31/2019 | P | CANC |
Jim Page
|
|
|
Rescheduled for 01AUG2019 per conversation with point of contact, this request is cancelled.
Please call clarence Phone #: ###-#### Inspection requested via web by Jessia Maxwell
|
Fees Due Hold | 6/17/2017 | | 9/13/2017 | | DONE |
Brittany Hill
|
|
|
|
Fees Due Hold | 6/6/2017 | | 6/16/2017 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 6/5/2017 | | 6/5/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/5/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/5/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/5/2017 | | 6/5/2017 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 3/2/2017 | | 3/2/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/2/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Sprinkler Plan Check | 2/21/2017 | | 2/21/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 2/21/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 2/21/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 2/17/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 2/17/2017 | | 2/17/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 2/14/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 14 2017 2:49PM
|