INSP-Final Inspection | 4/21/2017 | 4/21/2017 | 4/21/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 4/20/2017 | 4/20/2017 | 4/20/2017 | P | FAIL |
Troy Cobbley
|
|
|
I stopped at the project site to make contact with the contractor but could not find anyone. All doors are electronically secured. I did speak to a Pets Best representative but his supervisor was not in. No inspection performed.
|
INSP-Sprinkler Rough-in | 3/20/2017 | 3/20/2017 | 3/20/2017 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for several locations marked with todays date where piping is ok to cover.
|
Intake Approval | | | 3/6/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/6/2017 | | 3/6/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/6/2017 | | 3/6/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/6/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/6/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/6/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/6/2017 | | 3/6/2017 | | DONE |
Candy A. Nichols
|
|
|
|
(F) Reprint permit | | | 3/6/2017 | | DONE |
|
|
|
|
Application received | | | 2/24/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 24 2017 11:11AM
|