INSP-Final Inspection | 3/20/2017 | 3/24/2017 | 3/24/2017 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete
|
INSP-Final Inspection | 3/14/2017 | 3/15/2017 | 3/15/2017 | A | FAIL |
Troy Cobbley
|
|
|
Provide city approved plans/small documents, provide as-builts that match the installation for approval by plan review, provide testing.
|
INSP-Final Inspection | 3/13/2017 | 3/14/2017 | 3/14/2017 | A | CANC |
Troy Cobbley
|
|
|
Please Schedule for as close to 7AM as possible Phone #: ###-#### >> Inspection requested via web by David Oliver Inspection cancelled from web by: David Oliver
|
Permit Ready to Issue | | | 3/8/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/8/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/8/2017 | | 3/8/2017 | | DONE |
Christina Prado
|
|
|
|
Miscellaneous action | | | 3/6/2017 | | DONE |
|
|
|
Emailed Dave to remind him to do the upload complete task.
|
1st review completed | | | 3/6/2017 | | PASS |
|
|
|
|
Alarm Plan Check | 3/6/2017 | | 3/6/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/6/2017 | | DONE |
|
|
|
Plans approved with review comments and requirements.
|
Application received | | | 3/2/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 2 2017 8:14AM
|