INSP-Final Inspection | 9/24/2018 | 9/24/2018 | 9/24/2018 | P | PASS |
Jim Page
|
|
|
Final inspection for underground supply complete.
|
INSP-Supply line flush | 11/13/2017 | 11/17/2017 | 11/17/2017 | A | DONE |
Jim Page
|
|
|
Underground supply flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 8/31/2017 | 9/1/2017 | 9/1/2017 | A | CANC |
Jim Page
|
|
|
Call point of contact (Brad Westbrook ###-####) twice to try and schedule hydro test, received voicemail both times, left a message both times and did not get a call back, inspection request will need to be rescheduled.
|
INSP-Sprinkler Rough-in | 5/25/2017 | 5/26/2017 | 5/26/2017 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection for underground complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 5/17/2017 | 5/18/2017 | 5/18/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover inspection for underground complete, current install terminates approximately 60 feet east from 13th street, remaining underground to be installed at a later date, piping installed approved for cover.
|
Plan Modification Accepted | | | 5/8/2017 | | DONE |
|
|
|
|
Plan assigned to (Tim) | 5/8/2017 | | 5/8/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/8/2017 | | 5/8/2017 | | DONE |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/8/2017 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/8/2017 | | DONE |
|
|
|
as per Tim Frost-no fees due after plan mod
|
CHANGE STATUS TO (ISS) | | | 5/8/2017 | | DONE |
|
|
|
as per Tim Frost-no fees due after plan mod
|
INSP-Sprinkler Rough-in/Hydro | 3/31/2017 | 4/3/2017 | 4/3/2017 | A | PART |
Jim Page
|
|
|
Partial rough to cover for underground supply stub-in complete (Riser section of underground and piping penetrating the footing) Area inspected approved for cover.
|
Sprinkler Plan Check | 3/9/2017 | | 3/9/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/9/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/9/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/9/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/9/2017 | | 3/9/2017 | | DONE |
Brittany Hill
|
|
|
|
Intake Approval | | | 3/7/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/7/2017 | | 3/7/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/7/2017 | | 3/7/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 3/7/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 3/7/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Miscellaneous action | | | 3/7/2017 | | DONE |
|
|
|
as per Tim frost changed address from 301 S 13th St to 348 S 13th St
|
Application received | | | 3/2/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 2 2017 2:19PM
|