Permit Information
Permit NumberFIR17-00102
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 348 S 13TH ST
Project NameHilton Garden Inn - Boise
Customer Number 
ePlanReviewYes
Description
[Hilton Garden Inn - Boise - UDG only] - Quick Permit
New 6"X15'± C-900 underground piping and fittings with thrust blocks.
[BLD16-04480] - Foundation, site grading and utilities. No plumbing or electrical inside of the perimeter foundation is allowed under this permit. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/24/20189/24/20189/24/2018PPASS
DetailsJim Page
Final inspection for underground supply complete.
INSP-Supply line flush11/13/201711/17/201711/17/2017ADONE
DetailsJim Page
Underground supply flush complete.
INSP-Sprinkler Rough-in/Hydro8/31/20179/1/20179/1/2017ACANC
DetailsJim Page
Call point of contact (Brad Westbrook ###-####) twice to try and schedule hydro test, received voicemail both times, left a message both times and did not get a call back, inspection request will need to be rescheduled.
INSP-Sprinkler Rough-in5/25/20175/26/20175/26/2017PPASS
DetailsJim Page
Rough to cover inspection for underground complete, approved for cover.
INSP-Sprinkler Rough-in/Hydro5/17/20175/18/20175/18/2017APART
DetailsJim Page
Partial rough to cover inspection for underground complete, current install terminates approximately 60 feet east from 13th street, remaining underground to be installed at a later date, piping installed approved for cover.
Plan Modification Accepted  5/8/2017 DONE
Plan assigned to (Tim)5/8/2017 5/8/2017 DONE
DetailsTim Frost
Sprinkler Plan Check5/8/2017 5/8/2017 DONE
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  5/8/2017 DONE
Permit Ready to Issue  5/8/2017 DONE
as per Tim Frost-no fees due after plan mod
CHANGE STATUS TO (ISS)  5/8/2017 DONE
as per Tim Frost-no fees due after plan mod
INSP-Sprinkler Rough-in/Hydro3/31/20174/3/20174/3/2017APART
DetailsJim Page
Partial rough to cover for underground supply stub-in complete (Riser section of underground and piping penetrating the footing) Area inspected approved for cover.
Sprinkler Plan Check3/9/2017 3/9/2017 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  3/9/2017 DONE
DetailsTim Frost
Permit Ready to Issue  3/9/2017 DONE
Issue and Print Permit  3/9/2017 DONE
Inspection Record Card- Fire3/9/2017 3/9/2017 DONE
DetailsBrittany Hill
Intake Approval  3/7/2017 PASS
Plan assigned to (Tim)3/7/2017 3/7/2017 DONE
DetailsTim Frost
Sprinkler Plan Check3/7/2017 3/7/2017 FAIL
DetailsTim Frost
1st review completed  3/7/2017 FAIL
DetailsTim Frost
Miscellaneous action  3/7/2017 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Miscellaneous action  3/7/2017 DONE
as per Tim frost changed address from 301 S 13th St to 348 S 13th St
Application received  3/2/2017 DONE
Application submitted via PDS Online on Mar 2 2017 2:19PM