INSP-Final Inspection | 10/23/2017 | 10/26/2017 | 10/26/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Supervisory signals were verified by Lee at all three buildings today.
|
INSP-Final Inspection | 10/23/2017 | 10/24/2017 | 10/23/2017 | A | CANC |
Jim Page
|
|
|
Rafael Castillo w/ Lea Electric will be onsite for inspection Phone #: ###-#### >> Inspection requested via web by John Siewert Inspection cancelled from web by: John Siewert
|
INSP-Final Inspection | 9/6/2017 | 9/7/2017 | 9/7/2017 | A | PART |
Jim Page
|
|
|
Final fire alarm inspection partially complete, need to verify requirements with the fire alarm plan reviewer for audio/visual notification on the link between the grove hotel, century link arena as well as the district building.
|
INSP-Final Inspection | 9/5/2017 | 9/6/2017 | 9/6/2017 | P | CANC |
Jim Page
|
|
|
Inspection request will be rescheduled due to issues with a NAC panel, this inspection request is cancelled.
|
INSP-Final Inspection | 9/5/2017 | 9/6/2017 | 9/6/2017 | A | CANC |
Jim Page
|
|
|
John Phone #: ###-####
|
INSP-Final Inspection | 8/31/2017 | 9/5/2017 | 9/5/2017 | P | CANC |
Jim Page
|
|
|
Tech - Kc Strykowski
Consolidated with FIR16-00777 and FIR17-00340 Phone #: ###-#### >> Inspection requested via web by John Siewert Inspection cancelled from web by: John Siewert
|
CHANGE STATUS TO (REV) | | | 8/30/2017 | | DONE |
|
|
|
|
Alarm Plan Check | 8/30/2017 | | 8/30/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/30/2017 | | DONE |
|
|
|
Plan modification approved. No additional review comments.
|
Permit Ready to Issue | | | 8/30/2017 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 8/30/2017 | | DONE |
|
|
|
|
(F) Reprint permit | | | 8/30/2017 | | DONE |
|
|
|
|
Plan Modification Accepted | | | 8/29/2017 | | DONE |
|
|
|
|
Miscellaneous action | | | 8/22/2017 | | DONE |
|
|
|
eplanreview workflow opened for a plan modification at John Siewert's request.
|
INSP-Final Inspection | 8/15/2017 | 8/16/2017 | 8/16/2017 | P | FAIL |
Troy Cobbley
|
|
|
No city approved plans on site. No inspection performed. As previously stated plans need to be re-submitted and smoke evac zones need tested.
|
INSP-Final Inspection | 7/14/2017 | 7/17/2017 | 7/17/2017 | P | CANC |
Jim Page
|
|
|
Inspection of signals to neighboring buildings. Phone #: ###-#### >> Inspection requested via web by Chris Siewert Inspection cancelled from web by: Chris Siewert
|
INSP-Final Inspection | 6/29/2017 | 6/30/2017 | 6/30/2017 | P | PART |
Troy Cobbley
|
|
|
Temp c of o, phase 3 fire alarm is complete. Fire alarm plans need to be resubmitted for a plan mod due to changes
|
INSP-Final Inspection | 3/29/2017 | 3/30/2017 | 3/30/2017 | A | PART |
Jim Page
|
|
|
Partial final complete for fire alarm system. Area's inspected consist of link between GBAD, Century Link and Boise Center, audio visual devices tested good as well as escalator lobbies on level 1 and level 2. Area's requested for TCO passed/complete (GBAD, Century Link, Boise Center and elevated concourse between Boise Center and west stairwell)
|
INSP-Final Inspection | 3/29/2017 | 3/29/2017 | 3/29/2017 | P | CANC |
Jim Page
|
|
|
Scheduled for 30MAR2017
|
Permit Ready to Issue | | | 3/27/2017 | | DONE |
|
|
|
all requirements met
|
Issue and Print Permit | | | 3/27/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/27/2017 | | 3/27/2017 | | DONE |
Carlos Velazquez
|
|
|
|
Telephone call | | | 3/24/2017 | | DONE |
|
|
|
Called Jim to let him know that the floor plans for FA3 abd FA4 are pre-demo plans and that the as built drawings will be required to be updated with the new floor plans prior to acceptance.
|
Alarm Plan Check | 3/24/2017 | | 3/24/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/24/2017 | | DONE |
|
|
|
Plans approved with review comments and specific requirements.
|
Plan resubmittals received | | | 3/23/2017 | | DONE |
|
|
|
|
Miscellaneous action | | | 3/23/2017 | | DONE |
|
|
|
Scale graph appears to be incorrect on sheet 17-033-FA5. I emailed Jim regarding my concerns and asked him to verify their accuracy.
|
Miscellaneous action | | | 3/22/2017 | | DONE |
|
|
|
Jim Shilton emailed to inform me that he had forgotten to add elevator recall to the sequence matrix. I replyed to ask him to make the changes and email the revised drawing so it could be inserted.
|
Telephone call | | | 3/21/2017 | | DONE |
|
|
|
Spoke with Jamie Koenig of ZGA Architects. I explained the smoke control requirements and the need to determine how the floor plan changes affect the existing system. He looked into it with the mechanical engineer of record and determined what was required. He issued a letter explaining this and made it a requirement of the project. The letter has been uploaded into the Tidemark documents.
|
Plan resubmittals received | | | 3/21/2017 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 3/8/2017 | | 3/8/2017 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/8/2017 | | FAIL |
|
|
|
Failed pre-screen review. No smoke control zones shown, no smoke control operations indicated on matrix, magnetic door holders not shown. Emailed Jim Shilton informing him that this information is needed prior to review and if needed, the records department has archives of the previous retro-fit that shows the smoke control zones and sequence.
|
Telephone call | | | 3/8/2017 | | DONE |
|
|
|
Jim called to say he did not have access to any of the smoke control zone layout or programming information. Subsequently, I was able to find the information in PDS records and forwarded it to him via email. I informed him that zone modifications are required to be reviewed and approved by the mechanical engineer of record.
|
Application received | | | 3/7/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 7 2017 9:50PM
|