INSP-Final Inspection | 4/6/2017 | 4/7/2017 | 4/7/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Intake Approval | | | 3/23/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/23/2017 | | 3/23/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/23/2017 | | 3/23/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/23/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/23/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/23/2017 | | DONE |
|
|
|
all requirements met
|
Issue and Print Permit | | | 3/23/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/23/2017 | | 3/23/2017 | | DONE |
Carlos Velazquez
|
|
|
|
Application received | | | 3/22/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 22 2017 1:38PM
|