INSP-Final Inspection | 10/8/2017 | 10/9/2017 | 10/9/2017 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Final Inspection | 9/8/2017 | 9/11/2017 | 9/11/2017 | P | CANC |
Jim Page
|
|
|
Fire alarms are not ready, final fire sprinkler ispection will be scheduled to coincide with fire alarm final, this request is cancelled.
|
INSP-Supply line flush | 8/1/2017 | 8/2/2017 | 8/2/2017 | A | DONE |
Jim Page
|
|
|
Underground supply line flush complete
|
INSP-Supply line flush | 8/1/2017 | 8/2/2017 | 8/1/2017 | A | CANC |
Jim Page
|
|
|
Trying to coordinate a time with Stacy at Suez. Call Jake in AM to discuss. Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed.
|
INSP-Supply line flush | 7/20/2017 | 7/21/2017 | 7/21/2017 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled per Jake
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2017 | 6/28/2017 | 6/28/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for overhead fire sprinkler piping/tenting complete, approved for cover. Hydrostatic test for overhead fire sprinkler piping complete.
|
INSP-Sprinkler Rough-in/Hydro | 6/26/2017 | 6/27/2017 | 6/27/2017 | A | CANC |
Troy Cobbley
|
|
|
Can't do the hydro test until all of the heads have been cut in and piping installed
|
INSP-Sprinkler Rough-in/Hydro | 6/26/2017 | 6/26/2017 | 6/26/2017 | P | CANC |
Troy Cobbley
|
|
|
Please let Jake know when you are heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 6/22/2017 | 6/23/2017 | 6/23/2017 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact, Jake Phone #: ###-####, inspection will be rescheduled for a later date.
|
INSP-Sprinkler Rough-in/Hydro | 6/20/2017 | 6/21/2017 | 6/21/2017 | A | CANC |
Jim Page
|
|
|
Inspection request cancelled per conversation with point of contact, Jake Phone #: ###-####, inspection will be rescheduled for a later date.
|
Sprinkler Plan Check | 3/29/2017 | | 3/29/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/29/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/29/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/29/2017 | | DONE |
|
|
|
all requirements met
|
Issue and Print Permit | | | 3/29/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/29/2017 | | 3/29/2017 | | DONE |
Carlos Velazquez
|
|
|
|
Intake Approval | | | 3/28/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/28/2017 | | 3/28/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 3/27/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 27 2017 1:51AM
|