INSP-Final Inspection | 4/26/2017 | 4/27/2017 | 4/26/2017 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 4/18/2017 | 4/18/2017 | 4/18/2017 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
|
Intake Approval | | | 4/12/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 4/12/2017 | | 4/12/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/12/2017 | | 4/12/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/12/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/12/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/12/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/12/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/12/2017 | | 4/12/2017 | | DONE |
Christina Prado
|
|
|
|
Application received | | | 4/11/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 11 2017 2:11PM
|