INSP-Final Inspection | 11/2/2017 | 11/3/2017 | 11/3/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
Rick Phone #: ###-####
|
INSP-Final Inspection | 10/26/2017 | 10/27/2017 | 10/27/2017 | A | CANC |
Troy Cobbley
|
|
|
Not ready for final due to the project related fire alarm not being ready.
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2017 | 6/12/2017 | 6/12/2017 | P | PASS |
Jim Page
|
|
|
Overhead fire sprinkler hydrostatic test complete.
|
INSP-Sprinkler Rough-in | 6/9/2017 | 6/9/2017 | 6/9/2017 | P | PASS |
Jim Page
|
|
|
Rough in inspection for overhead fire sprinkler piping core and shell protection complete.
|
Intake Approval | | | 5/2/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/2/2017 | | 5/2/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/2/2017 | | 5/2/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/2/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/2/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/2/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/2/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/2/2017 | | 5/2/2017 | | DONE |
Brittany Hill
|
|
|
|
Application received | | | 5/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 1 2017 2:41PM
|