INSP-Final Inspection | 6/21/2017 | 6/21/2017 | 6/21/2017 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection for area of work passed/complete
|
INSP-Final Inspection | 6/15/2017 | 6/16/2017 | 6/16/2017 | A | FAIL |
Troy Cobbley
|
|
|
Door failed to function upon activation of the smoke detectors
|
Permit Ready to Issue | | | 5/17/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/17/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/17/2017 | | 5/17/2017 | | DONE |
Brittany Hill
|
|
|
|
Miscellaneous action | | | 5/15/2017 | | DONE |
|
|
|
John emailed a copy of the associated building permit BLD16-04356. Address is different than the one shown on this application. Directed John to coordinate the address correction with the permit desk.
|
Alarm Plan Check | 5/15/2017 | | 5/15/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/15/2017 | | DONE |
|
|
|
Quick permit plans approved as noted. No review comments.
|
Miscellaneous action | | | 5/9/2017 | | DONE |
|
|
|
John emailed to say the owner claims that a building permit was provided for 25 N. Phillippi but research through tidemark and Onbase does not reflect that. I responded with a request for the building permit number.
|
Miscellaneous action | | | 5/4/2017 | | DONE |
|
|
|
A building permit has not been applied for, regarding the installation of the roll door in the existing fire wall. I discussed the requirements with Carl Westfall and he indicated this type of alteration would require a review and permit.
|
Telephone call | | | 5/4/2017 | | DONE |
|
|
|
Called John Siewert to let him know that a building permit application and plan review would be required prior to issuance of the fire alarm pernmit. Once issued, the fire alarm permit can be released. He indicated the he will inform his prime contractor of the requirements. I followed up with an email to John that recaps our discussion.
|
Plan assigned to (Lee) | 5/4/2017 | | 5/4/2017 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 5/4/2017 | | PEND |
|
|
|
No building permit application has been submitted. Review is pending until that takes place.
|
Application received | | | 5/3/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 3 2017 9:19AM
|