INSP-Final Inspection | 1/23/2018 | 1/24/2018 | 1/24/2018 | A | PASS |
Jim Page
|
|
|
Final inspection for manual dry standpipe complete.
|
INSP-Sprinkler Rough-in/Hydro | 1/24/2018 | 1/24/2018 | 1/24/2018 | A | DONE |
Jim Page
|
|
|
Hydrostatic test for manual dry standpipe complete, no pressure loss observed at riser supplied gauge.
|
INSP-Sprinkler Rough-in/Hydro | 1/23/2018 | 1/24/2018 | 1/24/2018 | A | PASS |
Jim Page
|
|
|
Standpipe rough in inspection complete.
|
INSP-Final Inspection | 1/10/2018 | 1/16/2018 | 1/16/2018 | A | PART |
Jim Page
|
|
|
Partial final inspection complete for MANUAL DRY STANDPIPE, levels 1, 2 and 3 inspection complete.
|
INSP-Sprinkler Rough-in/Hydro | 1/9/2018 | 1/11/2018 | 1/11/2018 | P | PASS |
Troy Cobbley
|
|
|
24 hour air test on both systems passed
|
INSP-Sprinkler Rough-in/Hydro | 1/9/2018 | 1/10/2018 | 1/10/2018 | P | PART |
Jim Page
|
|
|
24 hour air test started on level 1 standpipe at 1PM with 41 PSI on both systems.
|
INSP-Final Inspection | 1/5/2018 | 1/8/2018 | 1/8/2018 | A | DONE |
Jim Page
|
|
|
Underground flush complete.
|
INSP-Sprinkler Rough-in/Hydro | 10/17/2017 | 10/17/2017 | 10/17/2017 | P | PASS |
Jim Page
|
|
|
Underground hydrostatic test complete.
|
Plan Modification Accepted | | | 8/22/2017 | | DONE |
|
|
|
|
Sprinkler Plan Check | 8/22/2017 | | 8/22/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/22/2017 | | DONE |
|
|
|
|
Intake Approval | | | 8/22/2017 | | PASS |
|
|
|
|
Permit Ready to Issue | | | 8/22/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/22/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/22/2017 | | 8/22/2017 | | DONE |
Brittany Hill
|
|
|
|
Sprinkler Plan Check | 5/17/2017 | | 5/17/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/17/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/17/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/17/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/17/2017 | | 5/17/2017 | | DONE |
Tisha Gallop
|
|
|
|
Sprinkler Plan Check | 5/8/2017 | | 5/8/2017 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 5/8/2017 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/8/2017 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Miscellaneous action | | | 5/8/2017 | | DONE |
|
|
|
Spoke with Ron Johnson on propose standpipe layout on two different occasions. He approved the layout even though the entire floor was not covered. He told me that the Boise City Fire Fighters carry 150' of hose not 100' as indicated in NFPA and IFC. I asked him to verify the FDC needed to be on the front of the building. He agreed. Ron, also said a fire pump was not need even though (3) outlets are on one floor. The outlets were arrange to be usable to the fire fighters without going far into the building to make a connection. This arrangement required one addtional outlet.
I told the FP contractor the above and that the hose outlets needed to be on the intermediate landing per Boise City.
|
Intake Approval | | | 5/5/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/5/2017 | | 5/5/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/4/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 4 2017 12:51PM
|