INSP-Final Inspection | 1/5/2018 | 1/5/2018 | 1/5/2018 | A | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection complete.
|
INSP-Final Inspection | 1/3/2018 | 1/4/2018 | 1/4/2018 | A | PART |
Jim Page
|
|
|
Partial final inspection complete for fire sprinklers, all hose valves need caps installed before permit can be finaled.
|
INSP-Final Inspection | 12/29/2017 | 1/3/2018 | 1/3/2018 | A | CANC |
Troy Cobbley
|
|
|
Paul Phone #: ###-####
|
INSP-Final Inspection | 12/22/2017 | 12/22/2017 | 12/22/2017 | P | PART |
Jim Page
|
|
|
Partial final inspection complete for overhead fire sprinklers, permit for fire sprinklers can be finaled when fire alarm associated components are inspected and passed.
|
INSP-Final Inspection | 12/20/2017 | 12/20/2017 | 12/21/2017 | P | CANC |
Troy Cobbley
|
|
|
No fire alarm permit scheduled.
Call Jake before heading out Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
INSP-Final Inspection | 12/19/2017 | 12/19/2017 | 12/19/2017 | P | CANC |
Jim Page
|
|
|
Call Jake before heading out Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 8/27/2017 | 8/28/2017 | 8/28/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for level 1 complete, approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/25/2017 | 8/25/2017 | 8/25/2017 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Anthony. I could not make it to the project site when Anthony needed me to meet.
|
INSP-Sprinkler Rough-in/Hydro | 8/24/2017 | 8/24/2017 | 8/24/2017 | P | FAIL |
Jim Page
|
|
|
Insulation needs to be removed where pipe is covered, overhead fire sprinkler piping could not be inspected in numerous area's due to cover from insulation. Hangers are overspaced in numerous area's on level 1, FDC piping going from riser to standpipe has no hangers/straps installed. Overhead fire sprinkler piping on level 1 cannot be covered until rough to cover inspection is complete and passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/23/2017 | 8/24/2017 | 8/24/2017 | A | PASS |
Jim Page
|
|
|
Hydrostatic test for level 1 complete
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2017 | 8/21/2017 | 8/21/2017 | A | FAIL |
Jim Page
|
|
|
Hydrostatic test not ready for level 1, system had a fitting that was not glued, hydrostatic test for level 1 will be rescheduled.
|
INSP-Sprinkler Rough-in | 8/16/2017 | 8/16/2017 | 8/16/2017 | A | PASS |
Jim Page
|
|
|
Tenting inspection complete, approved for cover.
|
INSP-Sprinkler Rough-in | 8/15/2017 | 8/15/2017 | 8/15/2017 | P | PASS |
Troy Cobbley
|
|
|
Third floor was not ready. Fourth floor is ok to cover. Heat for the piping enclosures was not installed yet and will need to be verified prior to a final.
|
INSP-Sprinkler Rough-in | 8/11/2017 | 8/14/2017 | 8/14/2017 | P | FAIL |
Jim Page
|
|
|
Tenting not complete on levels 3 and 4. Inspection stopped after finding numerous hangers overspaced on levels 3 and 4.
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2017 | 8/14/2017 | 8/14/2017 | P | PART |
Jim Page
|
|
|
Htdrostatic test complete for levels 2, 3 and 4. Level 1 to be completed at a later date.
|
INSP-Sprinkler Rough-in/Hydro | 8/11/2017 | 8/14/2017 | 8/11/2017 | A | CANC |
Jim Page
|
|
|
Call Jake before heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
|
INSP-Sprinkler Rough-in/Hydro | 6/27/2017 | 6/28/2017 | 6/28/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for standpipe complete, approved for cover. Hydrostatic test for standpipe complete.
|
INSP-Sprinkler Rough-in/Hydro | 6/26/2017 | 6/27/2017 | 6/27/2017 | A | FAIL |
Troy Cobbley
|
|
|
Standpipe hydro failed due to visable leak at the 90/check valve
|
INSP-Sprinkler Rough-in/Hydro | 6/26/2017 | 6/26/2017 | 6/26/2017 | P | CANC |
Troy Cobbley
|
|
|
Standpipe rough/hydro - let Jake know when you are heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
|
Permit Ready to Issue | | | 5/10/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/10/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/10/2017 | | 5/10/2017 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 5/9/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/9/2017 | | 5/9/2017 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 5/9/2017 | | 5/9/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/9/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/9/2017 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/8/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 8 2017 10:42AM
|