Permit Information
Permit NumberFIR17-00217
StatusFinaled
Name THORPE FIRE SPRINKLER SYSTEMS
Site Address 7364 W SAXTON DR
Project NameKensington Apts Bldg D OH
Customer Number 
ePlanReviewYes
Description
[Kensington Apartments - Building D]
The fire sprinkler scope of work consists of a NFPA 13R system for a four level apartment building. The system is supplied by 2” underground through a 2” backflow preventer to (4) 1½” flow control risers. The system piping is CPVC with extended coverage residential sprinklers. There is a manual dry standpipe system with (4) riser with a total of (12) outlets. The sprinkler header is connected to the manual standpipe.

[BLD15-01121] - The drawings are filed under BLD15-01118 in ePlanReview. The NFPA 13-R fire sprinkler system is used for occupancy and for story increase. To construct a 44,518 square foot four story apartment building (11,390 sq. ft. 1st story with two 3.c units, two 3.b units, three 2.c units, and one 2.g unit, 11,390 sq. ft. 2nd story with four 3.b units, three 2.c units, and one 2.g unit, 11,390 sq. ft. 3rd story with four 3.b units, three 2.c units, and one 2.g unit, 11,390 sq. ft. 4th story with four 2.d units, three 2.c units, and one 2.g unit) An elevator is provided in this building that serves all stories. All units in this building are required to comply as Type B dwelling units. Of those Type B dwelling units, 2 will also comply as Type A units. Work is to include concrete footings, concrete foundations, concrete slabs on grade, wood stud bearing walls, wood stud shear walls, fiberglass shingles, fiber-cement board siding, manufactured stone veneer, a 2-hr elevator shaft, 1-hr dwelling unit separations, .5-hr minimum fire-resistance-rated corridors with 20 minute smoke- and draft-control doors, exterior exit stairways fire rated like the corridors, steel stairways with concrete treads, interior nonbearing walls, millwork, and finishes. Special Inspection is required for soils and for concrete. The roof truss design is a deferred submittal item. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13-R and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/5/20181/5/20181/5/2018APASS
DetailsJim Page
Final fire sprinkler inspection complete.
INSP-Final Inspection1/3/20181/4/20181/4/2018APART
DetailsJim Page
Partial final inspection complete for fire sprinklers, all hose valves need caps installed before permit can be finaled.
INSP-Final Inspection12/29/20171/3/20181/3/2018ACANC
DetailsTroy Cobbley
Paul Phone #: ###-####
INSP-Final Inspection12/22/201712/22/201712/22/2017PPART
DetailsJim Page
Partial final inspection complete for overhead fire sprinklers, permit for fire sprinklers can be finaled when fire alarm associated components are inspected and passed.
INSP-Final Inspection12/20/201712/20/201712/21/2017PCANC
DetailsTroy Cobbley
No fire alarm permit scheduled.

Call Jake before heading out Phone #: ###-#### Inspection requested via web by Anthony Minichiello
INSP-Final Inspection12/19/201712/19/201712/19/2017PCANC
DetailsJim Page
Call Jake before heading out Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro8/27/20178/28/20178/28/2017APASS
DetailsJim Page
Rough to cover inspection for level 1 complete, approved for cover.
INSP-Sprinkler Rough-in/Hydro8/25/20178/25/20178/25/2017PCANC
DetailsTroy Cobbley
Cancel per Anthony. I could not make it to the project site when Anthony needed me to meet.
INSP-Sprinkler Rough-in/Hydro8/24/20178/24/20178/24/2017PFAIL
DetailsJim Page
Insulation needs to be removed where pipe is covered, overhead fire sprinkler piping could not be inspected in numerous area's due to cover from insulation. Hangers are overspaced in numerous area's on level 1, FDC piping going from riser to standpipe has no hangers/straps installed. Overhead fire sprinkler piping on level 1 cannot be covered until rough to cover inspection is complete and passed.
INSP-Sprinkler Rough-in/Hydro8/23/20178/24/20178/24/2017APASS
DetailsJim Page
Hydrostatic test for level 1 complete
INSP-Sprinkler Rough-in/Hydro8/18/20178/21/20178/21/2017AFAIL
DetailsJim Page
Hydrostatic test not ready for level 1, system had a fitting that was not glued, hydrostatic test for level 1 will be rescheduled.
INSP-Sprinkler Rough-in8/16/20178/16/20178/16/2017APASS
DetailsJim Page
Tenting inspection complete, approved for cover.
INSP-Sprinkler Rough-in8/15/20178/15/20178/15/2017PPASS
DetailsTroy Cobbley
Third floor was not ready. Fourth floor is ok to cover. Heat for the piping enclosures was not installed yet and will need to be verified prior to a final.
INSP-Sprinkler Rough-in8/11/20178/14/20178/14/2017PFAIL
DetailsJim Page
Tenting not complete on levels 3 and 4. Inspection stopped after finding numerous hangers overspaced on levels 3 and 4.
INSP-Sprinkler Rough-in/Hydro8/11/20178/14/20178/14/2017PPART
DetailsJim Page
Htdrostatic test complete for levels 2, 3 and 4. Level 1 to be completed at a later date.
INSP-Sprinkler Rough-in/Hydro8/11/20178/14/20178/11/2017ACANC
DetailsJim Page
Call Jake before heading out, thanks! Phone #: ###-#### >> Inspection requested via web by Anthony Minichiello Inspection cancelled from web by: Anthony Minichiello
INSP-Sprinkler Rough-in/Hydro6/27/20176/28/20176/28/2017APASS
DetailsJim Page
Rough to cover inspection for standpipe complete, approved for cover. Hydrostatic test for standpipe complete.
INSP-Sprinkler Rough-in/Hydro6/26/20176/27/20176/27/2017AFAIL
DetailsTroy Cobbley
Standpipe hydro failed due to visable leak at the 90/check valve
INSP-Sprinkler Rough-in/Hydro6/26/20176/26/20176/26/2017PCANC
DetailsTroy Cobbley
Standpipe rough/hydro - let Jake know when you are heading out, thanks! Phone #: ###-#### Inspection requested via web by Anthony Minichiello
Permit Ready to Issue  5/10/2017 DONE
Issue and Print Permit  5/10/2017 DONE
Inspection Record Card- Fire5/10/2017 5/10/2017 DONE
DetailsChristina Prado
Intake Approval  5/9/2017 PASS
Plan assigned to (Tim)5/9/2017 5/9/2017 DONE
DetailsTim Frost
Sprinkler Plan Check5/9/2017 5/9/2017 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  5/9/2017 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  5/9/2017 DONE
DetailsTim Frost
Application received  5/8/2017 DONE
Application submitted via PDS Online on May 8 2017 10:42AM