INSP-Final Inspection | 12/4/2017 | 12/4/2017 | 12/4/2017 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection for building 2 passed/complete.
|
INSP-Alarm Testing | 12/1/2017 | 12/4/2017 | 12/4/2017 | A | DONE |
Jim Page
|
|
|
Fire alarm tetsing complete.
|
INSP-Alarm Testing | 11/28/2017 | 11/30/2017 | 11/30/2017 | A | FAIL |
Jim Page
|
|
|
Smoke curtians did not drop when associated smoke detector was activated. Install does not match city approved drawings, contractor needs to resubmit as-built drawings. Levels 1, 2, 3 and 4 are missing audio visual devices, audio visual devices in parking garage are overspaced. FDC bell did not activate with dry system trip.
|
INSP-Final Inspection | 11/28/2017 | 11/28/2017 | 11/28/2017 | P | FAIL |
Jim Page
|
|
|
Fire panel needs to be System is Normal before inspection can be started.
|
Alarm Plan Check | 8/31/2017 | | 8/31/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/31/2017 | | DONE |
|
|
|
Plans approved with review comments and requirements.
|
Permit Ready to Issue | | | 8/31/2017 | | DONE |
|
|
|
all met
|
Issue and Print Permit | | | 8/31/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/31/2017 | | 8/31/2017 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Plan resubmittals received | | | 8/30/2017 | | DONE |
|
|
|
|
Miscellaneous action | | | 8/28/2017 | | DONE |
|
|
|
Emailed Cindy to let her know that the latest drawing 22 still does not match the other calculation drawings. I provided sided by side drawings showing some of the calculation errors and firmly informed them that they need to go through all drawings and calculation sheets and provide corrections.
|
Miscellaneous action | | | 8/25/2017 | | DONE |
|
|
|
Received updated calculation sheet 22 from Cindy.
|
Miscellaneous action | | | 8/23/2017 | | DONE |
|
|
|
Emailed Cindy to remine her that I am still waiting on corrected calculations.
|
Miscellaneous action | | | 8/17/2017 | | DONE |
|
|
|
Emailed Cindy to let her know that her circuit and panel calculations do not appear to have been updated to show changes made on this resubmittal. Requested updates be provided.
|
Miscellaneous action | | | 8/17/2017 | | DONE |
|
|
|
Updated calculations received for sheets 22 - 26. Numbers on sheet ww are incorrect. Emailed Cindy requesting corrections.
|
1st review completed | | | 8/2/2017 | | FAIL |
|
|
|
See review comments.
|
Plan resubmittals received | | | 7/31/2017 | | DONE |
|
|
|
|
Miscellaneous action | | | 7/31/2017 | | DONE |
|
|
|
Engineer of record approval was not included. I emailed Cindy to let her know that our review cannot be completed without it and asked her to email it to me as soon as she receives it. 8-1-17 received engineer of record approval.
|
Miscellaneous action | | | 6/6/2017 | | DONE |
|
|
|
Cindy Barnes finally submitted printed drawings for the building and the two other buildings at this site under a new tidemark permit (FIR17-00256). I contacted her on the phone and informed her that each building needed to be submitted for seperate permits. I also informed her of various design items that needed correction prior to resubmittal. She will upload to the correct projects in eplanreview. (FIR17-00232, 00233 & 00234). FIR17-00256 is to be voided.
|
Application received | | | 5/15/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 15 2017 1:59PM
|