INSP-Final Inspection | 6/16/2017 | 6/19/2017 | 6/19/2017 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection for area of work associated with this permit passed/complete.
|
Plan resubmittals received | | | 5/23/2017 | | DONE |
|
|
|
|
Miscellaneous action | | | 5/23/2017 | | DONE |
|
|
|
John emailed to indicate he will be providing release control at the fire alarm panel. All other building permit review requirements will be provided by Simplex Grinnell - the access contractor.
|
Alarm Plan Check | 5/23/2017 | | 5/23/2017 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/23/2017 | | DONE |
|
|
|
Quick permit approved with review comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/23/2017 | | DONE |
|
|
|
as per Lee-he's done with plan review
|
Permit Ready to Issue | | | 5/23/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 5/23/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/23/2017 | | 5/23/2017 | | DONE |
Candy A. Nichols
|
|
|
|
Application received | | | 5/22/2017 | | DONE |
|
|
|
Application submitted via PDS Online on May 22 2017 1:24PM
|
Miscellaneous action | | | 5/22/2017 | | DONE |
|
|
|
Manual release at door and FACP missing so application failed and John notified vie email of requirements.
|
Plan assigned to (Lee) | 5/22/2017 | | 5/22/2017 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 5/22/2017 | | FAIL |
|
|
|
|