INSP-Final Inspection | 12/4/2017 | 12/6/2017 | 12/6/2017 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush passed
|
INSP-Sprinkler Rough-in/Hydro | 12/4/2017 | 12/5/2017 | 12/5/2017 | P | PASS |
Troy Cobbley
|
|
|
Hydrotest for overhead shell system passed
|
INSP-Final Inspection | 12/4/2017 | 12/6/2017 | 12/4/2017 | P | CANC |
Troy Cobbley
|
|
|
We would like to coordinate this in conjunction with final for the Curtis restaurant TI FIR 17-00690 Phone #: ###-#### >> Inspection requested via web by Jeff Packham Inspection cancelled from web by: Jeff Packham
|
INSP-Sprinkler Rough-in | 12/1/2017 | 12/1/2017 | 12/1/2017 | A | PASS |
Troy Cobbley
|
|
|
Need all typical items for final, signs/stickers..ect and also need the pipe sizing to the heads under hvac units and doors addressed and heads changed out at the unit heaters.
|
INSP-Supply line flush | 11/28/2017 | 11/28/2017 | 11/28/2017 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Supply line flush | 11/14/2017 | 11/14/2017 | 11/14/2017 | P | CANC |
Troy Cobbley
|
|
|
Cancel per Troy Phone #: ###-####
|
INSP-Sprinkler Rough-in | 10/30/2017 | 10/30/2017 | 10/30/2017 | P | PASS |
Troy Cobbley
|
|
|
Piping/pendant in riser room is ok to cover.
|
INSP-Conference | 10/24/2017 | 10/25/2017 | 10/25/2017 | A | DONE |
Troy Cobbley
|
|
|
Jeff Packham and I discussed getting the shell/core signed off as well as the T.I.
|
INSP-Sprinkler Rough-in/Hydro | 9/25/2017 | 9/25/2017 | 9/25/2017 | P | PASS |
Troy Cobbley
|
|
|
UG hydro passed
|
INSP-Sprinkler Rough-in | 9/13/2017 | 9/14/2017 | 9/13/2017 | A | PASS |
Jim Page
|
|
|
Rough to cover inspection for remaining underground complete, underground supply approved for cover.
|
INSP-Sprinkler Rough-in/Hydro | 8/22/2017 | 8/23/2017 | 8/23/2017 | A | PASS |
Troy Cobbley
|
|
|
Not ready for hydro. Rough-in passed but still waiting for the piping to be installed under overhead doors. Tim Frost approved the revised earthquake attachments. Also letter was received as required in note #1 of the review comments.
Randy Phone #: ###-####
|
INSP-Sprinkler Rough-in | 8/2/2017 | 8/2/2017 | 8/2/2017 | P | PASS |
Troy Cobbley
|
|
|
Todays inspection was to verify hanger attachments to the roof structure prior to cover. Attachments can be covered.
|
INSP-Sprinkler Rough-in | 6/28/2017 | 6/28/2017 | 6/28/2017 | P | PASS |
Troy Cobbley
|
|
|
IBR only is ok to cover. The remaining piping will be installed later. No thrust block, mechanical restraint is being used.
|
Sprinkler Plan Check | 6/12/2017 | | 6/12/2017 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 6/12/2017 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/12/2017 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 6/12/2017 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/12/2017 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/12/2017 | | 6/12/2017 | | DONE |
Brittany Hill
|
|
|
|
Intake Approval | | | 6/2/2017 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 6/2/2017 | | 6/2/2017 | | DONE |
Tim Frost
|
|
|
|
Miscellaneous action | | | 6/2/2017 | | PEND |
|
|
|
On hold pending switching design to Spec Warehouse provision.
|
Application received | | | 6/1/2017 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 1 2017 3:56PM
|